New Chemical Manufacturing Facilities for Carbon Fiber at Kashima Plant
First written in FY2023-Q1. 2 of 4 entries say "Softened", first in FY2024-Q2. Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025AdvancedAnnual report
「Machinery and equipment・・・Kashima Plant Carbon-fiber chemical production facility ¥528 million」
For the carbon-fiber chemical production facility at the Kashima Plant, the company disclosed an increase of ¥528 million in machinery and equipment, indicating that the existing new-facility plan has progressed to the stage of recording the equipment. - FY2024SoftenedAnnual report
「Filing company Kashima Plant Kamisu City, Ibaraki Prefecture Carbon-fiber chemical production facility (new facility) ¥686 million ¥61 million Internal funds June 2022 April 2025 1,184 tonnes」
The scheduled completion date for the carbon-fiber chemical production facility was changed from October 2024 to April 2025. The company disclosed a planned investment of ¥686 million, payments made to date of ¥61 million, and an annual capacity increase of 1,184 tonnes. - FY2024-Q2SoftenedAnnual report
「Filing company Kashima Plant Ibaraki Prefecture Kamisu City Chemicals for carbon fiber Production facility (New facility) Plastic and Fiber-Related Industries ¥686 million ¥1 million Internal funds June 2022 October 2024 (Note 2) 1,184 tonnes (Note 2) The scheduled completion date for the investment has been changed from May 2024 to October 2024.」
For the carbon-fiber chemical production facility at the Kashima Plant, the company disclosed a planned investment of ¥686 million, payments made to date of ¥1 million, and an annual capacity increase of 1,184 tonnes, and changed the scheduled completion date from May to October 2024. - FY2023-Q1First statedAnnual report
「Filing company Kashima Plant Ibaraki Prefecture Kamisu City Chemicals for carbon fiber Production facility (New facility) Plastic and Fiber-Related Industries ¥686 million - Internal funds June 2022 May 2024 1,184 tonnes」
The company newly finalized plans to install a carbon-fiber chemical production facility at the Kashima Plant. The planned investment is ¥686 million, with construction scheduled to begin in June 2022 and be completed in May 2024. The facility is expected to increase annual capacity by 1,184 tonnes once completed.