Construction of New Antistatic Agent Manufacturing Facilities at a Thai Subsidiary

First written in FY2021-Q2. 1 of 3 entries say "Restated". Latest entry: FY2021.

3entries
2years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2021-Q2 – FY2021-Q32020: 120202021: 22021
Same theme, other companies
Construction of New Antistatic Agent Manufacturing Facilities at a Thai SubsidiaryA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2021AdvancedAnnual report

    「Sanyo Kasei (Thailand) Limited Rayong Province, Thailand Antistatic-agent production facilities (new construction) Plastic and textile industry-related fields 3,600 2,564 Internal funds and borrowings February 2019 April 2022 1,500」

    For the antistatic-agent production facilities in Thailand, the company disclosed that the amount already paid had increased to ¥2.564 billion, with total investment of ¥3.6 billion, additional annual production capacity of 1,500 tonnes, and scheduled completion in April 2022.
  2. FY2021-Q3RestatedAnnual report

    「Sanyo Kasei (Thailand) Limited Rayong Province, Thailand Antistatic-agent production facilities (new construction) Plastic and textile industry-related fields 3,600 2,358 Internal funds and borrowings February 2019 April 2022 1,500 (Note) 1. The scheduled completion date for the investment was changed from April 2021 to April 2022.」

    For the antistatic-agent production facilities at the Thai subsidiary, the company continued to report a total investment of ¥3.6 billion, ¥2.358 billion already paid, additional annual capacity of 1,500 tonnes, and scheduled completion in April 2022.
  3. FY2021-Q2First statedAnnual report

    「Sanyo Kasei (Thailand) Limited Rayong Province, Thailand Antistatic-agent production facilities (new construction) Plastic and textile industry-related fields 3,600 2,243 Internal funds and borrowings February 2019 April 2022 1,500 (Note) 1. The scheduled completion date for the investment was changed from April 2021 to April 2022.」

    For the antistatic-agent production facilities at the Thai subsidiary, the company reported a total investment of ¥3.6 billion, ¥2.243 billion already paid, and additional annual capacity of 1,500 tonnes after completion, and changed the scheduled completion date from April 2021 to April 2022.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Sanyo Chemical Industries yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Construction of New Antistatic Agent Manufacturing Facilities at a Thai Subsidiary | SANYO CHEMICAL INDUSTRIES,LTD. (4471) | Komori