New battery materials research facilities at the Kinuura Plant
First written in FY2016. 1 of 3 entries say "Advanced", first in FY2017-Q2. Latest entry: FY2017-Q3.
No other company in this theme has enough history to compare yet.
- FY2017-Q3SoftenedAnnual report
「Reporting company Kinuura Plant Handa, Aichi Research and development facility for battery materials Information, electrical and electronics-related industries ¥500 million — Internal funds June 2016 March 2017」
The battery materials research and development facility has an investment amount of ¥500 million, began construction in June 2016, and is scheduled for completion in March 2017, changed from the previous scheduled completion date to March. - FY2017-Q2AdvancedAnnual report
「Reporting company Kinuura Plant Handa, Aichi Research and development facility for battery materials Information, electrical and electronics-related industries Planned investment: ¥500 million Internal funds Started June 2016 Scheduled for completion January 2017」
The company invested ¥500 million in the research and development facility for battery materials, with construction beginning in June 2016 and completion scheduled for January 2017, indicating progress at the planning stage. - FY2016First statedAnnual report
「The company decided to establish a new battery materials research facility at the Kinuura Plant, in addition to its existing research facilities at the Kyoto head office and the Katsura Research Center.」
The company decided to establish a battery materials research facility in connection with a new business platform in the energy and electronics fields.