Komori
PBsystems (4447) · InitiativeAdvanced

Investment in Server, Storage and Network Infrastructure

First written in FY2019. 5 of 6 entries say "Advanced", first in FY2020. Latest entry: FY2025.

6entries
7years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2019AdvancedFY2020 – FY20252019: 12020: 120202021: 020212022: 120222023: 120232024: 120242025: 12025
Same theme, other companies
Business Infrastructure Investment through Servers and SoftwareA theme 34 companies write about · 0 as a headwind · 39 as a tailwind

21 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 34 companies compared. The sentences above are computed from all 34.
Full recordFilings, disclosures and news, newest first
  1. FY2025AdvancedAnnual report

    「Total capital expenditures for the fiscal year were ¥12.101 million. The main item was the expansion of the engineering habitat in Fukuoka, Fukuoka Prefecture (¥7.809 million), aimed at strengthening personnel and improving productivity in the secure cloud systems business.」

    The Company expanded its engineering habitat and established an additional capital expenditure plan of ¥25 million through September 2026 for development-environment equipment, virtual-environment equipment, licenses and other items.
  2. FY2024AdvancedAnnual report

    「Server, storage and software, among other items ¥10 million - Internal funds October 2024 September 2025」

    The Company established a ¥10 million capital expenditure plan funded with internal funds for the period from October 2024 to September 2025, covering servers, storage and software, among other items.
  3. FY2023AdvancedAnnual report

    「The Company has established a capital expenditure plan comprising ¥30 million for servers, storage and software, among other items, ¥5 million for internal system upgrades, and ¥20 million in initial costs related to opening an engineering habitat.」

    In addition to the existing investment plan for servers, storage and other items, the Company specified upgrades to internal systems and the cost of opening an engineering habitat as uses of the capital increase proceeds and working capital.
  4. FY2022AdvancedAnnual report

    「Server, storage and software, among other items ¥35 million ¥2.318 million Proceeds from capital increase October 2022 September 2024」

    The Company established a capital expenditure plan for servers, storage and software, among other items, with a total cost of ¥35 million, ¥2.318 million already paid, and completion scheduled for September 2024.
  5. FY2020AdvancedAnnual report

    「Server, storage and network equipment and software, among other items」

    Under the plan with a planned investment of ¥15 million, ¥4.181 million had already been paid, and the plan continued with completion scheduled for September 2021.
  6. FY2019First statedAnnual report

    「Server, storage and network equipment and software, among other items」

    This capital expenditure plan commenced in April 2020, was scheduled for completion in September 2021, and had a planned investment of ¥15 million.
Moved together

"Strengthening Relationships with Major Partners and Developing Mid-Tier Corporate Customers" moved the same way as this thread, in the same document, in 5 of its 6 moves.

555444★123456
  1. ★This thread
  2. 1Strengthening Relationships with Major Partners and Developing Mid-Tier Corporate Customers5×
  3. 2Growth opportunity in Japan's private cloud market5×
  4. 3Reliance on Interest-Bearing Debt and Interest Rate Fluctuations5×
  5. 4Advancing the Cloud Business Through the New Concept of “Essential Resilience”4×
  6. 5Expansion into new fields, including outside the 4D King amusement park and overseas4×
  7. 6Sustained Growth of the Secure Cloud System Business4×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for PBsystems yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.