Komori
Occurring Fact4390IPS,Inc.Information & Communications, Services and Others

Supplementary Information on the Execution of a Grant Agreement with the U.S. Trade and Development Agency (USTDA)

The U.S. Trade and Development Agency (USTDA) has formally decided to provide funding for a feasibility study (FS) by InfiniVAN Inc., part of our group, on the Silangan submarine cable project along the eastern coast of the Philippines. The background to the project and its positioning within the group’s medium- to long-term business strategy were explained. At this stage, the project remains in the FS phase, and construction, commercialization and the impact on business performance have not been determined.

Worth reading
35Immaterial
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Avoiding a definitive answer
How definitive the wording is.

Execution of a Grant Agreement with the U.S. Trade and Development Agency (USTDA)

Subject Entity

InfiniVAN Inc. (our group company)

Target Locations / Products

Eastern coast of the Philippines; Baler large-scale landing station; Silangan Submarine Cable System; 7–15 international submarine cable landing stations; and APECO and other data centers

This disclosure11/24/2026
Cause

To build a secure, high-capacity domestic submarine cable network along the eastern coast of the Philippines, extending from Luzon Island to Mindanao Island

Impact on Earnings Forecast

The impact on business performance will be assessed in detail based on progress in specific business conditions and other factors, and we will promptly disclose any matters requiring disclosure.

Related procedures

Court or authority

U.S. Trade and Development Agency (USTDA)

Company response

Investigation structure

U.S.-based Lambda Consulting is scheduled to conduct the FS

Outlook

Construction of the Baler large-scale landing station is being advanced with the aim of completing it within 2026. The FS is scheduled to cover market demand analysis, technical and economic feasibility assessments, marine surveys for route selection, and design planning for 7–15 landing stations. The impact on business performance will be assessed in detail based on progress in specific business conditions and other factors.

Planned follow-up disclosure

We will promptly announce any matters requiring disclosure should they arise.

Event that occurred
ItemDetails
Event nameExecution of a Grant Agreement with the U.S. Trade and Development Agency (USTDA)
Subject EntityInfiniVAN Inc. (our group company)
Target Locations / ProductsEastern coast of the Philippines; Baler large-scale landing station; Silangan Submarine Cable System; 7–15 international submarine cable landing stations; and APECO and other data centers
CauseTo build a secure, high-capacity domestic submarine cable network along the eastern coast of the Philippines, extending from Luzon Island to Mindanao Island
Impact on Earnings ForecastThe impact on business performance will be assessed in detail based on progress in specific business conditions and other factors, and we will promptly disclose any matters requiring disclosure.
Court or authorityU.S. Trade and Development Agency (USTDA)
Investigation structureU.S.-based Lambda Consulting is scheduled to conduct the FS
OutlookConstruction of the Baler large-scale landing station is being advanced with the aim of completing it within 2026. The FS is scheduled to cover market demand analysis, technical and economic feasibility assessments, marine surveys for route selection, and design planning for 7–15 landing stations. The impact on business performance will be assessed in detail based on progress in specific business conditions and other factors.
Planned follow-up disclosureWe will promptly announce any matters requiring disclosure should they arise.
Items this document does not state (16)
Date of occurrenceDate recognized / date notice receivedAmount of Impact on Business PerformanceAccounting period in which recognizedType of litigation or proceedingPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionSuspended operationsScheduled resumption dateMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

To help investors understand the background to the grant agreement disclosed on November 20 and its positioning within our group’s business strategy. The impact on business performance will be assessed in detail based on progress in specific business conditions and other factors.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.