Investment in the renewal, expansion and rationalisation of production facilities
First written in FY2022. 7 of 8 entries say "Advanced", first in FY2024. Latest entry: 2026-08-07.
123 other companies' latest entry also says "Advanced".
- 2026-08-07AdvancedResults
「なお、固定資産については、マナック株式会社福山工場における金属管理分析ルーム・新事務所棟の竣工に伴い、建設仮勘定から建物及び構築物等への振替を行っております。」
福山工場の金属管理分析ルーム・新事務所棟が竣工し、建設仮勘定から固定資産への振替を行った。 - FY2026AdvancedAnnual report
「The total investment in property, plant and equipment by the Group during the consolidated fiscal year was ¥1,749 million, including construction in progress.」
Capital investment in FY2026 amounted to ¥1,749 million. Investments were made in a metal management analysis room, fine chemical production facilities and a new office building, among other assets. The Company also presented plans to expand production facilities and install facilities related to metal management technology at the Fukuyama Plant from 2026 to 2027. - FY2026-H1AdvancedAnnual report
「Cash used in investing activities was ¥678 million, compared with ¥171 million used in the same period of the previous year. This was mainly attributable to the acquisition of property, plant and equipment.」
The Company invested ¥678 million in FY2026-H1, primarily in the acquisition of property, plant and equipment, increasing spending associated with capital investment from ¥171 million in the same period of the previous year. Property, plant and equipment also increased as a result of major capital investments. - FY2025-H1AdvancedAnnual report
「Cash used in investing activities was ¥171 million, compared with ¥210 million used in the same period of the previous year. This was mainly attributable to the acquisition of property, plant and equipment.」
The Company spent ¥171 million on investing activities during the interim consolidated accounting period, primarily for the acquisition of property, plant and equipment. - FY2024AdvancedAnnual report
「The total investment in property, plant and equipment by the Group during the consolidated fiscal year was ¥296 million.」
The Company invested ¥296 million in property, plant and equipment in FY2024. In addition, it presented plans to renew the flame-retardant production facilities at the Fukuyama Plant, with investments of ¥80 million each commencing and being completed in January 2025 and being completed in March of the same year. - FY2022First statedAnnual report
「The total investment in property, plant and equipment by the Group during the consolidated fiscal year was ¥664 million.」
The Company invested ¥664 million in property, plant and equipment during the fiscal year, including the installation and renewal of production facilities at the Fukuyama Plant and other locations. It also presented a plan to expand fine chemical production facilities from October 2022 to June 2023.