Revised forecast
Fiscal year ending March 2026 · Full yearPrevious forecast published Dated 6 January 2026The bar length represents the relative magnitude of change, based on the item that changed the most in this document. The percentage change shown by the dotted line is calculated from the two reported figures because the company did not provide the rate.
For the first data center project in Japan and the first in Australia, deliveries of servers and other equipment have been delayed, pushing the start of revenue recognition from service provision into the fiscal year ending March 2027. Meanwhile, service volumes for additional orders exceeded expectations in response to strong demand for use. In addition, the non-recognition of ¥818 million in share-based compensation expense, lower interest payments due to the borrowing balance being below the assumed level, and the non-recognition of ¥2,304 million in depreciation and amortization expense affected profit.
| Item | Details |
|---|---|
| Net Sales | 37,273 million yen → 33,601 million yen(-9.9%) |
| Operating profit | 3,498 million yen → 3,635 million yen(+3.9%) |
| Ordinary income | 2,972 million yen → 3,457 million yen(+16.3%) |
| Profit attributable to owners of the parent | 1,908 million yen → 2,804 million yen(+47.0%) |
| Net income per share | 59.34 yen and sen → 115.57 yen and sen |
| Fiscal Period Covered | Fiscal year ending March 2026 |
| Period Covered | Full year |
| Publication date of previous forecast | Dated 6 January 2026 |
| Previous-period results | Fiscal year ended March 2025: net sales ¥2,942 million, operating loss ¥496 million, ordinary loss ¥169 million, net loss attributable to owners of the parent ¥654 million, and negative earnings per share of ¥37.40 |
| Reason for the revision | For the first data center project in Japan and the first in Australia, deliveries of servers and other equipment have been delayed, pushing the start of revenue recognition from service provision into the fiscal year ending March 2027. Meanwhile, service volumes for additional orders exceeded expectations in response to strong demand for use. In addition, the non-recognition of ¥818 million in share-based compensation expense, lower interest payments due to the borrowing balance being below the assumed level, and the non-recognition of ¥2,304 million in depreciation and amortization expense affected profit. |
| Consolidated / non-consolidated | Consolidated |
Items this document does not state (2)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.For 2 data center projects, deliveries of servers and related materials have been delayed by heightened geopolitical risks and the construction boom in AI data centers, pushing the start of service revenue recognition into the fiscal year ending March 2027 and resulting in a reduction to the net sales forecast. Meanwhile, profit forecasts have been revised upward due to service volumes for additional orders exceeding expectations, the non-recognition of ¥818 million in share-based compensation expense, and lower interest payments resulting from the assumed borrowing balance being below expectations, among other factors.