Further Delay in Completion of Alberta-Pacific’s Log Crane Replacement Project
First written in FY2019-Q2. 3 of 8 entries say "Restated". Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025Completion rescheduled again to May 2025Annual report
「Aging log-yard crane replacement project CAD million 25 CAD million 23 Internal funds May 2022 May 2025 Stable operations」
The Alberta-Pacific log-yard crane replacement project has a total cost of CAD 25 million, with CAD 23 million paid to date and completion scheduled for May 2025. - FY2024Completion rescheduled to October 2024Annual report
「Aging log-yard crane replacement project CAD million 23 Amount paid to date 7 Internal funds May 2022 October 2024 Stable operations」
The Alberta-Pacific log-yard crane replacement project has a total cost of CAD 23 million, with CAD 7 million paid to date and completion scheduled for October 2024. - FY2023RestatedAnnual report
「Aging log-yard crane replacement project; C$21 million; 0; self-financed; May 2022; July 2024; stable operations.」
The disclosure reiterates the plan for Alberta-Pacific's log-yard crane replacement project, with a total cost of C$21 million and scheduled completion in July 2024. - FY2023-Q3RestatedAnnual report
「Alberta-Pacific Forest Industries Inc.; head office and mill, Alberta, Canada; pulp and paper business; replacement of aging log-yard cranes; C$21 million; self-financed; commenced May 2022; scheduled completion July 2024; stable operations.」
The disclosure reiterates the plan for Alberta-Pacific's aging log-yard crane replacement project, with a total cost of C$21 million, commencement in May 2022 and scheduled completion in July 2024. - FY2023-Q2RestatedAnnual report
「Alberta-Pacific Forest Industries Inc.; head office and mill, Alberta, Canada; pulp and paper business; replacement of aging log-yard cranes; C$21 million; self-financed; commenced May 2022; scheduled completion July 2024; stable operations.」
The disclosure reiterates the plan for Alberta-Pacific's aging log-yard crane replacement project, with a total cost of C$21 million, commencement in May 2022 and scheduled completion in July 2024. - FY2023-Q1Revised project scheduleAnnual report
「Alberta-Pacific Forest Industries Inc.; head office and mill, Alberta, Canada; pulp and paper business; replacement of aging log-yard cranes; C$21 million; self-financed; commenced May 2022; scheduled completion July 2024; stable operations.」
The disclosure newly presents a plan for Alberta-Pacific's aging log-yard crane replacement project, with a total cost of C$21 million, commencement in May 2022 and scheduled completion in July 2024. - FY2019Completion schedule changed again to June 2019Annual report
「Alberta-Pacific Forest Industries Inc.; head office and mill; log crane replacement project; ¥1,018 million. Planned investment: total, C$17 million; amount paid to date, C$14 million; commenced, January 2018; completion, June 2019; stable operations.」
¥1,018 million was invested during the fiscal year in the log crane replacement project. Total investment was C$17 million, of which C$14 million had already been paid, with completion scheduled for June 2019. The schedule was changed again from the previously stated April 2019 date. - FY2019-Q2First statedAnnual report
「The scheduled completion date for the log crane replacement project at Alberta-Pacific Forest Industries Inc. has been changed from September 2018 to April 2019.」
The scheduled completion date for Alberta-Pacific’s log crane replacement project changed from September 2018 to April 2019.