Hokuetsu (3865) · InitiativeCompletion rescheduled again to May 2025

Further Delay in Completion of Alberta-Pacific’s Log Crane Replacement Project

First written in FY2019-Q2. 3 of 8 entries say "Restated". Latest entry: FY2025.

8entries
8years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseOtherFY2019-Q2 – FY20252018: 12019: 120192020: 020202021: 020212022: 220222023: 220232024: 120242025: 12025
Same theme, other companies
Alberta-Pacific log yard crane renewal workA theme 1 companies write about · 1 as a headwind · 0 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2025Completion rescheduled again to May 2025Annual report

    「Aging log-yard crane replacement project CAD million 25 CAD million 23 Internal funds May 2022 May 2025 Stable operations」

    The Alberta-Pacific log-yard crane replacement project has a total cost of CAD 25 million, with CAD 23 million paid to date and completion scheduled for May 2025.
  2. FY2024Completion rescheduled to October 2024Annual report

    「Aging log-yard crane replacement project CAD million 23 Amount paid to date 7 Internal funds May 2022 October 2024 Stable operations」

    The Alberta-Pacific log-yard crane replacement project has a total cost of CAD 23 million, with CAD 7 million paid to date and completion scheduled for October 2024.
  3. FY2023RestatedAnnual report

    「Aging log-yard crane replacement project; C$21 million; 0; self-financed; May 2022; July 2024; stable operations.」

    The disclosure reiterates the plan for Alberta-Pacific's log-yard crane replacement project, with a total cost of C$21 million and scheduled completion in July 2024.
  4. FY2023-Q3RestatedAnnual report

    「Alberta-Pacific Forest Industries Inc.; head office and mill, Alberta, Canada; pulp and paper business; replacement of aging log-yard cranes; C$21 million; self-financed; commenced May 2022; scheduled completion July 2024; stable operations.」

    The disclosure reiterates the plan for Alberta-Pacific's aging log-yard crane replacement project, with a total cost of C$21 million, commencement in May 2022 and scheduled completion in July 2024.
  5. FY2023-Q2RestatedAnnual report

    「Alberta-Pacific Forest Industries Inc.; head office and mill, Alberta, Canada; pulp and paper business; replacement of aging log-yard cranes; C$21 million; self-financed; commenced May 2022; scheduled completion July 2024; stable operations.」

    The disclosure reiterates the plan for Alberta-Pacific's aging log-yard crane replacement project, with a total cost of C$21 million, commencement in May 2022 and scheduled completion in July 2024.
  6. FY2023-Q1Revised project scheduleAnnual report

    「Alberta-Pacific Forest Industries Inc.; head office and mill, Alberta, Canada; pulp and paper business; replacement of aging log-yard cranes; C$21 million; self-financed; commenced May 2022; scheduled completion July 2024; stable operations.」

    The disclosure newly presents a plan for Alberta-Pacific's aging log-yard crane replacement project, with a total cost of C$21 million, commencement in May 2022 and scheduled completion in July 2024.
  7. FY2019Completion schedule changed again to June 2019Annual report

    「Alberta-Pacific Forest Industries Inc.; head office and mill; log crane replacement project; ¥1,018 million. Planned investment: total, C$17 million; amount paid to date, C$14 million; commenced, January 2018; completion, June 2019; stable operations.」

    ¥1,018 million was invested during the fiscal year in the log crane replacement project. Total investment was C$17 million, of which C$14 million had already been paid, with completion scheduled for June 2019. The schedule was changed again from the previously stated April 2019 date.
  8. FY2019-Q2First statedAnnual report

    「The scheduled completion date for the log crane replacement project at Alberta-Pacific Forest Industries Inc. has been changed from September 2018 to April 2019.」

    The scheduled completion date for Alberta-Pacific’s log crane replacement project changed from September 2018 to April 2019.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Hokuetsu yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.