Komori
Management planning3825Remixpoint,inc.Retail

Notice concerning the sixth site to enter the balancing market: a grid-scale battery storage facility in Ota, Shimane Prefecture

The NC Ota City Nima-cho Battery Storage Facility in Ota, Shimane Prefecture, began operations for the balancing market on 17 November 2026, bringing the company's total number of participating sites to 6. Operations combining JEPX and the balancing market are now possible, and monthly sales are expected to be approximately ¥15 million. However, this is not included in the previously disclosed segment earnings forecast for the fiscal year ending March 2027.

Worth reading
34Immaterial
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
15
¥ million/month
Wording
Conditional
How definitive the wording is.

Items stated in the management plan

<Supplementary Explanatory Material> Future Ownership and Sales Plans and Investment Scale for the Energy Storage Solutions BusinessPlan period Through the fiscal year ending March 2029
Publication date 17 November 2026
What happened to the previous planCumulative total of 48 sites, including 25 company-owned sites → 12 company-owned sites, including projects under development-75.0%Calculated from the two disclosed figures
Key initiatives
01Development and acquisition of battery storage facilities
02Commencement of operations at owned battery storage facilities and expansion of participating markets
03Operations combining the various markets in line with market conditions
04Participation in JEPX, the balancing market and the capacity market
Plan assumptionsCurrent market trading prices, The company's simulations and the aggregator's actual performance data, among other factors, May fluctuate depending on market conditions and other factors
Segment targetSegment Battery Storage Solutions Business / Target fiscal year Fiscal year ending March 2027 / Net Sales ¥7,045 million / Segment profit ¥1,002 million
Non-financial targetsIndicator Cumulative number of high-voltage grid-scale battery storage facilities developed / Target value 48 sites / Timing Through the fiscal year ending March 2029, Indicator Number of company-owned battery storage facilities / Target value 25 sites / Timing Through the fiscal year ending March 2029
Risks identified by the company
Actual sales may fluctuate depending on market conditions and other factors
These are estimates based on market trading prices and other factors and do not guarantee actual sales
The timing of power receipt may change depending on progress in the construction process and other factors
Items stated in the management plan
ItemDetails
Plan name<Supplementary Explanatory Material> Future Ownership and Sales Plans and Investment Scale for the Energy Storage Solutions Business
Plan periodThrough the fiscal year ending March 2029
Segment targetSegment Battery Storage Solutions Business / Target fiscal year Fiscal year ending March 2027 / Net Sales ¥7,045 million / Segment profit ¥1,002 million
Non-financial targetsIndicator Cumulative number of high-voltage grid-scale battery storage facilities developed / Target value 48 sites / Timing Through the fiscal year ending March 2029, Indicator Number of company-owned battery storage facilities / Target value 25 sites / Timing Through the fiscal year ending March 2029
Plan assumptionsCurrent market trading prices, The company's simulations and the aggregator's actual performance data, among other factors, May fluctuate depending on market conditions and other factors
Key initiativesDevelopment and acquisition of battery storage facilities, Commencement of operations at owned battery storage facilities and expansion of participating markets, Operations combining the various markets in line with market conditions, Participation in JEPX, the balancing market and the capacity market
Results under the previous planCumulative total of 48 sites, including 25 company-owned sites → 12 company-owned sites, including projects under development
Risks identifiedActual sales may fluctuate depending on market conditions and other factors, These are estimates based on market trading prices and other factors and do not guarantee actual sales, The timing of power receipt may change depending on progress in the construction process and other factors
Publication date17 November 2026
Items this document does not state (16)
Progress against the planSales TargetOperating profit targetOperating profit margin targetNet income targetROE targetROIC targetPayout ratio / DOE policyTreasury share acquisition policyCost of capitalSelf-assessment of PBR and share priceTotal investment planInvestment amount by sectorReason for revision or withdrawalSize of the Target MarketDate of board resolution

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

By providing balancing capacity in the balancing market, the company can combine this with charge and discharge operations based on JEPX market prices, thereby expanding revenue opportunities and maximising revenue in line with market conditions.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice concerning the sixth site to enter the balancing market: a grid-scale battery storage facility in Ota, Shimane Prefecture | Remixpoint,inc. (3825) timely disclosure | Komori