[Business Progress in the Grid-Scale Battery Storage Sales Business] The externally sold project "Osaki City Narukoonsen Aza Hoshinuma Battery Storage Facility" has commenced foundation work

Foundation construction for the “Osaki City Naruko Onsen Aza Hoshinuma Battery Storage Facility,” which is being developed for an external customer, began in earnest at the end of August 2026. Power reception and handover to the customer are scheduled to begin in December 2026.

Worth reading
68In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
1977
kW (rated output)
Wording
Conditional
How definitive the wording is.

Announced details

Osaki City Naruko Onsen Aza Hoshinuma Battery Storage Facility (provisional name) / Grid-Scale Battery Storage Facility Equipment Sales
Applicable field (uses covered by this announcement)

For customer companies seeking to enter the grid-scale battery storage business

Launch dateDecember 2026 (power reception and handover scheduled to begin)
Relationship between the counterparty and the company
Remixpoint,inc.3825
Relationship with the Company

We sell battery storage facility equipment, with 美吉建設株式会社 as the customer. Development and EPC services are being provided by 株式会社シールエンジニアリング.

Counterparty美吉建設株式会社
Location (as indicated in this announcement)

Osaki, Miyagi Prefecture

Rated output: 1,977 kW; rated capacity: 7,740 kWh

In this announcement the company addresses none of Contract Value / Offering price / Impact on Business Performance.

Announced details
ItemDetails
Names of Products / Services CoveredOsaki City Naruko Onsen Aza Hoshinuma Battery Storage Facility (provisional name) / Grid-Scale Battery Storage Facility Equipment Sales
Counterparty美吉建設株式会社
Relationship with the CompanyWe sell battery storage facility equipment, with 美吉建設株式会社 as the customer. Development and EPC services are being provided by 株式会社シールエンジニアリング.
Launch dateDecember 2026 (power reception and handover scheduled to begin)
Applicable areaFor customer companies seeking to enter the grid-scale battery storage business
LocationOsaki, Miyagi Prefecture
Location scaleRated output: 1,977 kW; rated capacity: 7,740 kWh
Items this document does not state (11)
Counterparty overviewContract ValueOffering priceContract DateAward/certification nameAwarding / certifying bodyRegistration number and expiry dateQuantitative EffectsUsage historyImpact on Business PerformanceSource

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

To steadily advance construction, power reception and handover for projects already ordered during the current fiscal year, and expand the external sales business as a growth driver for the energy storage solutions business.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
[Business Progress in the Grid-Scale Battery Storage Sales Business] The externally sold project "Osaki City Narukoonsen Aza Hoshinuma Battery Storage Facility" has commenced foundation work | Remixpoint,inc. (3825) timely disclosure | Komori