Construction Begins on External Sales Project “Ogano Town, Ryokami Susuki 838-1 Battery Storage Facility” in the Grid-Scale Battery Storage Business — Key Milestone Toward the Full-Scale Rollout of the Sales Model

Construction began on a grid-scale battery storage facility to be sold to an external customer, and a groundbreaking ceremony was held on 28 July 2026. Power reception and handover are scheduled for November 2026.

Worth reading
59In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
8359
kWh (rated capacity)
Wording
Conditional
How definitive the wording is.

Announced details

Saitama Prefecture, Chichibu District, Ogano Town, Ryokami Susuki 838-1 Battery Storage Facility (tentative name) / grid-scale battery storage sales business
Applicable field (uses covered by this announcement)

Grid-scale battery storage business; power grid and energy infrastructure

Launch dateScheduled commencement of power reception: November 2026; scheduled handover: November 2026
What the company reported numerically
Usage history

One of 4 projects for which orders have been received during the current fiscal year

Relationship between the counterparty and the company
Remixpoint,inc.3825
Relationship with the Company

株式会社シールエンジニアリング is a subsidiary of the Company. 株式会社シールエンジニアリング is responsible for development and EPC, while the Company group leads the project end to end, from land acquisition, business feasibility simulations, design and construction, equipment procurement, and grid connection consultations through operations and maintenance.

Location (as indicated in this announcement)

Chichibu District, Saitama Prefecture

Rated output: 1,990 kW; rated capacity: 8,359 kWh
Impact on Business Performance

The Company aims to expand sales revenue from its external sales business and strengthen its earnings base.

The company does not address Contract Value / Offering price.

Announced details
ItemDetails
Names of Products / Services CoveredSaitama Prefecture, Chichibu District, Ogano Town, Ryokami Susuki 838-1 Battery Storage Facility (tentative name) / grid-scale battery storage sales business
Relationship with the Company株式会社シールエンジニアリング is a subsidiary of the Company. 株式会社シールエンジニアリング is responsible for development and EPC, while the Company group leads the project end to end, from land acquisition, business feasibility simulations, design and construction, equipment procurement, and grid connection consultations through operations and maintenance.
Launch dateScheduled commencement of power reception: November 2026; scheduled handover: November 2026
Applicable areaGrid-scale battery storage business; power grid and energy infrastructure
LocationChichibu District, Saitama Prefecture
Location scaleRated output: 1,990 kW; rated capacity: 8,359 kWh
Usage historyOne of 4 projects for which orders have been received during the current fiscal year
Impact on Business PerformanceThe Company aims to expand sales revenue from its external sales business and strengthen its earnings base.
Items this document does not state (10)
CounterpartyCounterparty overviewContract ValueOffering priceContract DateAward/certification nameAwarding / certifying bodyRegistration number and expiry dateQuantitative EffectsSource

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

To continuously build up external sales projects, expand sales revenue, and strengthen the earnings base together with projects owned by the Company.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Construction Begins on External Sales Project “Ogano Town, Ryokami Susuki 838-1 Battery Storage Facility” in the Grid-Scale Battery Storage Business — Key Milestone Toward the Full-Scale Rollout of the Sales Model | Remixpoint,inc. (3825) timely disclosure | Komori