Komori
Business Alliances3777Environment Friendly Holdings Corp.Information and Communications, Services and Others

Decision on the Second Repowering Project in Collaboration with Huawei Japan and S-Energy

The No. 2 repowering project to be carried out at the Waseda Renewable Energy Power Plant in Misawa, Aomori Prefecture, has been decided as part of the collaboration with Huawei Japan and S-Energy. The power plant operator and S-Energy's Japanese subsidiary will enter into an EPC contract, under which Huawei Japan products will be adopted.

Worth reading
31Immaterial
Scored from 4 of 5 sections
Direction
Improvement
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Definitive
How definitive the wording is.

Agreements reached under this partnership

Business Alliances
3777Environment Friendly Holdings Corp.
Alliance partnerHuawei Technologies Japan K.K. (Huawei Japan) / S-Energy Co.,Ltd. / S-Energy Japan Co., Ltd.
Details of the alliance
  1. 1

    Consideration of collaboration in the digital power business

  2. 2

    Collaboration on the repowering business for solar power plants in Japan

  3. 3

    Huawei Japan products will be adopted under the EPC contract

These are items that the documents state the two companies will work on. The lines above and below represent arrangements between the two companies.

Impact on Business Performance

The impact on our consolidated results for the fiscal year ending December 2026 is currently expected to be minor.

Agreements reached under this partnership
ItemDetails
Name of alliance partnerHuawei Technologies Japan K.K. (Huawei Japan), S-Energy Co.,Ltd., S-Energy Japan Co., Ltd.
Type of allianceBusiness Alliances
Details of the allianceConsideration of collaboration in the digital power business, Collaboration on the repowering business for solar power plants in Japan, Huawei Japan products will be adopted under the EPC contract
Impact on Business PerformanceThe impact on our consolidated results for the fiscal year ending December 2026 is currently expected to be minor.
Items this document does not state (19)
Alliance partner's business activitiesAlliance partner's locationAlliance partner's capitalAlliance partner's net salesAlliance partner's operating incomeNumber of shares acquiredAcquisition priceShareholding ratioOverview of the joint ventureOwnership ratioDispatch of directors and officersContract PeriodNumerical targets under the allianceShareholding PolicyDate of board resolutionContract DateAlliance start dateShare Acquisition Date and Payment DateChange in major shareholders

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The importance of repowering and enhancing the sophistication of operations to increase the value of existing facilities has grown against the backdrop of aging solar power generation equipment and changes in operating conditions. In addition, our group aims to promote sustainable energy solutions.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Decision on the Second Repowering Project in Collaboration with Huawei Japan and S-Energy | Environment Friendly Holdings Corp. (3777) timely disclosure | Komori