Internet Initiative Japan (3774) · TargetAchieved
Start of Operations at the Shiroi Company-Owned Data Center in the First Half of Fiscal 2019
First written in FY2018-Q3. 1 of 3 entries say "Restated". Latest entry: FY2019.
3entries
2years
0from disclosures
How it moved
Same theme, other companies
Construction and Operations of the Shiroi In-House Data CenterA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2019AchievedAnnual report
「The system-module-based Shiroi Data Center Campus opened at the beginning of May this year as scheduled,」
The company stated that the target for beginning operations at the Shiroi Data Center was achieved when the facility opened in early May 2019. - FY2018RestatedAnnual report
「For our data center in Shiroi, Chiba Prefecture, we plan to finance ¥3,000 million of construction costs through bank borrowings, begin construction in August 2018, and complete it in March 2019.」
The company reconfirmed its construction plan for the in-house Shiroi Data Center, involving an investment of ¥3,000 million and completion scheduled for March 2019. - FY2018-Q3First statedAnnual report
「As the first phase, we will progressively build power receiving facilities and system modules with capacity for approximately 1,000 racks. As part of this project, we plan capital investment of more than ¥3 billion in fiscal 2018 and plan to begin operations in the first half of fiscal 2019.」
The first phase will have capacity for approximately 1,000 racks, with more than ¥3 billion to be invested in fiscal 2018 and operations planned to begin in the first half of fiscal 2019.