Tokushu Tokai Paper (3708) · InitiativeRestated
Increasing power generation capacity through the installation of gas engines
First written in FY2018. 2 of 4 entries say "Restated". Latest entry: FY2020-Q3.
4entries
3years
0from disclosures
How it moved
Same theme, other companies
Increasing power generation capacity through the installation of gas enginesA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2020-Q3RestatedAnnual report
「In addition, higher depreciation and other expenses associated with the start of operations of the new gas engine at the Mishima Mill resulted in a substantial decline in profit.」
The company continues to disclose higher depreciation and other expenses associated with the start of operations of the new gas engine at the Mishima Mill. - FY2020-Q2RestatedAnnual report
「In addition, a gas engine began operating at the Mishima Mill in January. This is intended to reduce costs while reducing the environmental impact.」
Cost reduction and environmental impact reduction efforts have continued following the start of operations of the gas engine at the Mishima Mill. - FY2020-Q1AchievedAnnual report
「In addition, a gas engine began operating at the Mishima Mill in January. This is intended to reduce costs while reducing the environmental impact.」
The gas engine at the Mishima Mill began operating in January, bringing the equipment installation into operation. It is intended to reduce costs and the environmental impact. - FY2018First statedAnnual report
「Gas engine installation work」
The planned investment is ¥1,140 million. Work began in May 2017 and is scheduled for completion in December 2018. The additional capacity after completion is expected to be 7,800 kW.