Asulina (3647) · RiskRestated
Risk of Grid Connection Refusal or Restrictions and Changes in Legal and Regulatory Requirements
First written in FY2017. 1 of 2 entries say "Restated". Latest entry: FY2018.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Revisions to Sales Plans Due to Competition for Solar Power Projects and Grid Interconnection DelaysA theme 7 companies write about · 8 as a headwind · 0 as a tailwind
0 other companies' latest entry also says "Restated".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2018RestatedAnnual report
「If laws and regulations governing the Group's business are enacted in the future, including through the application of new laws or the enactment of additional laws, the Group's performance may be affected by increased costs and other factors as it responds to those regulations.」
The risk of response costs and an impact on performance arising from the enactment or application of laws and regulations governing the business remains ongoing. - FY2017First statedAnnual report
「The performance of our Group may be affected by intensifying competition among power generators, refusal or restriction of grid connections by power companies, and the enactment or amendment of laws and regulations.」
For the solar power generation business, refusal or restriction of grid connections and the enactment or amendment of regulations, in addition to competition, are identified as specific risks.