Risk of Prolonged Development or Project Abandonment in Solar Power Plant Development

First written in FY2018. 1 of 4 entries say "Worsened", first in FY2021. Latest entry: FY2023.

4entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2018WorsenedFY2021MitigatedFY20222018: 12019: 020192020: 020202021: 020212022: 220222023: 12023
Same theme, other companies

3 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2023RestatedAnnual report

    「When acquiring candidate sites for solar power plant development, the Company’s group conducts thorough preliminary project investigations and due diligence, identifies development risks, and has a policy of developing only projects for which no material risks are expected.」

    The risks of development delays or abandonment due to permitting, nearby residents and dealings with the authorities, as well as the policy of selecting projects through preliminary investigations and due diligence, continue to be disclosed.
  2. FY2022MitigatedAnnual report

    「When acquiring candidate sites for solar power plant development, the Company’s group conducts thorough preliminary project investigations and due diligence, identifies development risks, and has a policy of developing only projects for which no material risks are expected.」

    In response to the risk of prolonged development or abandonment, the Company disclosed a policy of conducting preliminary investigations and due diligence before acquiring candidate sites and selecting projects accordingly.
  3. FY2021WorsenedAnnual report

    「Development may also have to be suspended if, for example, nearby residents oppose the project or the relevant authorities withhold their consent.」

    In addition to the previously disclosed risks of delays or abandonment due to laws, regulations and permitting procedures, opposition from nearby residents and the withholding of consent by the relevant authorities are now expressly identified.
  4. FY2018First statedAnnual report

    「Depending on the scale of a solar power plant development project, it may be subject to restrictions under laws and ordinances, including the Forest Act and environmental laws, and the application procedures may be complex and extensive. The permitting process may also take longer than expected. Consequently, if the period from securing the site to constructing the plant is significantly extended or circumstances arise that make it necessary to abandon development of the project midway, this could affect the performance of the Company’s group.」

    The disclosure describes the risk that regulations under the Forest Act, environmental laws and other legislation, as well as permitting procedures, could extend the period from securing a site to constructing a power plant or lead to abandonment of the project.
Moved together

"Internal Control and Staffing Expansion Risks Associated with Small Organizations" moved the same way as this thread, in the same document, in 2 of its 4 moves.

2★1
  1. ★This thread
  2. 1Internal Control and Staffing Expansion Risks Associated with Small Organizations2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Asulina's next results are scheduled for 2026-10-13. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Risk of Prolonged Development or Project Abandonment in Solar Power Plant Development | ASULINA Co.,Ltd. (3647) | Komori