「As part of the Group's capital investment plan, ¥2,700 million will be invested in data center facilities, equipment, software, and other items at Mitsubishi Research Institute DCS Co., Ltd. from October 2024 to September 2025, and ¥5,198 million in data center facilities, including the renewal of extra-high-voltage receiving and transforming equipment, from September 2023 to July 2027.」
For data center investment at the Chiba Information Center and other locations, new facility and renewal plans totaling ¥2,700 million and ¥5,198 million, together with their completion dates, are described. - FY2023AdvancedAnnual report
「Mitsubishi Research Institute DCS Co., Ltd. Chiba Information Center Other Shinagawa-ku, Tokyo Inzai, Chiba Prefecture Other IT services Data center facilities, equipment, software, etc. 7,500 - Internal funds October 2023 September 2024」
A new investment plan of ¥7,500 million for data center facilities, equipment, and software at the Chiba Information Center and other locations is described, with work scheduled to begin in October 2023 and be completed in September 2024. - FY2022-Q2AdvancedAnnual report
「Mitsubishi Research Institute DCS Co., Ltd. Chiba Information Center Shinagawa-ku, Tokyo Inzai, Chiba Prefecture IT services Data center facilities 2,053 - Internal funds February 2022 September 2023」
A new capital investment plan for data center facilities at the Chiba Information Center has been finalized, involving ¥2,053 million of investment using internal funds, beginning in February 2022 and scheduled for completion in September 2023. - FY2020AdvancedAnnual report
「For data center facilities, equipment, software, and other items at Mitsubishi Research Institute DCS Co., Ltd.'s Chiba Information Center and other locations, the planned investment amount is ¥4,654 million. Work will begin using internal funds in October 2020, with completion scheduled for September 2021.」
Following the previous year's ¥3,626 million plan, the next capital investment plan of ¥4,654 million for the Chiba Information Center and other facilities has been specified. - FY2019AdvancedAnnual report
「During the consolidated fiscal year, capital investment totaled ¥5,361 million. In IT services, ¥1,250 million was invested in property, plant and equipment and ¥3,523 million in intangible assets. The main investment was in software for customer services at Mitsubishi Research Institute DCS Co., Ltd. In addition, ¥3,626 million will be invested in data center facilities, equipment, software, and other items at the Chiba Information Center and other locations as part of a major new construction and renovation plan, with completion scheduled between October 2019 and September 2020.」
For the Chiba Information Center and other facilities, the company reports the current year's IT services capital investment results as well as the next investment plan of ¥3,626 million for the period from October 2019 to September 2020. - FY2019-Q3Updated with third-quarter capital investment resultsAnnual report
「Leased assets Mitsubishi Research Institute DCS Co., Ltd. Chiba Information Center (Inzai, Chiba Prefecture) IT services Software 2,761 Finance lease December 2018」
The finance-lease acquisition of software for IT services at the Chiba Information Center is reported at a carrying amount of ¥2,761 million. - FY2019-Q2Updated with second-quarter capital investment resultsAnnual report
「Leased assets Mitsubishi Research Institute DCS Co., Ltd. Chiba Information Center (Inzai, Chiba Prefecture) IT services Software 2,917 Finance lease December 2018」
The equipment results have been updated to show the acquisition in December 2018 of ¥2,917 million of software for IT services at the Chiba Information Center through a finance lease. - FY2019-Q1AdvancedAnnual report
「Leased assets Mitsubishi Research Institute DCS Co., Ltd. Chiba Information Center (Inzai, Chiba Prefecture) IT services Software 3,073 Finance lease December 2018」
The company reports the acquisition in December 2018 of ¥3,073 million of software for IT services at the Chiba Information Center through a finance lease. - FY2017AdvancedAnnual report
「As of the end of the consolidated fiscal year, major plans for new construction and renovation of facilities consisted of data center facilities, equipment, software, and other items at Mitsubishi Research Institute DCS Co., Ltd.'s Chiba Information Center and other locations. The planned investment amount is ¥3,650 million, work will begin using internal funds in October 2017, and completion is scheduled for September 2018.」
Following the previous year's investment plan for the Chiba Information Center and other facilities, the next capital investment plan of ¥3,650 million for the period from October 2017 to September 2018 has been specified. - FY2016First statedAnnual report
「Mitsubishi Research Institute DCS Co., Ltd. Chiba Information Center Other IT services Data center facilities, equipment, software, etc. 2,827 - Internal funds October 2016 September 2017」
For the Chiba Information Center and other facilities, a total of ¥2,827 million was invested in data center facilities, equipment, and software using internal funds, with completion scheduled for September 2017.