Risk of operational disruption and asset damage from the fire at the Hamamatsu facility
First written in FY2024. 3 of 3 entries say "Materialised", first in FY2024. Latest entry: FY2025.
3entries
2years
0from disclosures
How it moved
Same theme, other companies
Production disruption, asset damage and losses from the Hamamatsu facility fireA theme 1 companies write about · 1 as a headwind · 0 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2025MaterialisedAnnual report
「Insurance proceeds received: ¥32.330 million」
For the fire at the Hamamatsu facility, the company recognized ¥32.330 million in insurance proceeds and ¥38.034 million in fire losses for the full fiscal year, with the impact of the asset damage reflected in the accounts. - FY2025-H1MaterialisedAnnual report
「Insurance proceeds received: ¥32.330 million」
For the fire at the Hamamatsu facility, the company recognized ¥32.330 million in insurance proceeds and, at the same time, ¥38.034 million in fire losses as an extraordinary loss during the current interim consolidated accounting period. The impact of the fire-related asset damage was reflected in the accounts. - FY2024MaterialisedAnnual report
「A fire occurred on 25 April 2024 at our Hamamatsu facility in Hamamatsu, Shizuoka. Fluff and dust inside the exhaust duct of the singeing machine in the scouring and bleaching equipment ignited, and the fire spread to approximately 25 square meters of part of the plant, causing damage to some property, plant and equipment and inventories.」
A fire occurred at the Hamamatsu facility after the fiscal year-end, damaging approximately 25 square meters of part of the plant as well as property, plant and equipment and inventories. Restoration work began on 26 April, and normal operations resumed on 7 May.