Komori
Other Disclosures350ADIGITAL GRID CorporationElectricity and gas

Maniwa Solar Power Plant Begins Operations at Former Golf Course Site, to Supply Environmental Value to LY Corporation for 20 Years

The solar power plant in Maniwa, Okayama Prefecture, began commercial operations on 15 August 2026. Through a virtual PPA, it will supply the environmental value of the electricity generated to LY Corporation for 20 years.

Worth reading
71In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
85000000
Approximately 85 million kWh per year
Wording
Conditional
How definitive the wording is.

Announced details

Maniwa Solar Power PlantRE Bridge®GPA® (virtual PPA)
Applicable field (uses covered by this announcement)

Renewable energy; electricity and environmental value trading

Launch date15 August 2026 (commercial operations commenced; actual)
What the company reported numerically
Quantitative Effects

LY Corporation is expected to reduce greenhouse gas emissions by approximately 740,000 tonnes over 20 years

Relationship between the counterparty and the company
DIGITAL GRID Corporation350A
Relationship with the Company

Through a virtual PPA, the environmental value of the Maniwa Solar Power Plant will be supplied to LY Corporation for 20 years. Through RE Bridge® (a platform that matches electricity consumers with generators), the Company forecasts power generation, manages supply and demand, and sells electricity in the market.

CounterpartyLINEヤフー株式会社

Head office: Chiyoda-ku, Tokyo; Representative Director, President and CEO: Izawa Tsuyoshi (出澤剛)

Award/certification name

No. 1 in Japan in the Energy & Utilities category of the 2026 Asia-Pacific High-Growth Companies ranking; FY2025 Climate Change Action Environment Minister's Award

Location (as indicated in this announcement)

Maniwa, Okayama Prefecture

Expected annual generation of approximately 85 million kWh

In this announcement the company addresses none of Contract Value / Offering price / Impact on Business Performance.

Source (materials cited by the company)

Company research (stated to be the largest in Japan as of December 2024)

Announced details
ItemDetails
Names of Products / Services CoveredManiwa Solar Power Plant, RE Bridge®, GPA® (virtual PPA)
CounterpartyLINEヤフー株式会社
Counterparty overviewHead office: Chiyoda-ku, Tokyo; Representative Director, President and CEO: Izawa Tsuyoshi (出澤剛)
Relationship with the CompanyThrough a virtual PPA, the environmental value of the Maniwa Solar Power Plant will be supplied to LY Corporation for 20 years. Through RE Bridge® (a platform that matches electricity consumers with generators), the Company forecasts power generation, manages supply and demand, and sells electricity in the market.
Launch date15 August 2026 (commercial operations commenced; actual)
Applicable areaRenewable energy; electricity and environmental value trading
Award/certification nameNo. 1 in Japan in the Energy & Utilities category of the 2026 Asia-Pacific High-Growth Companies ranking; FY2025 Climate Change Action Environment Minister's Award
LocationManiwa, Okayama Prefecture
Location scaleExpected annual generation of approximately 85 million kWh
Quantitative EffectsLY Corporation is expected to reduce greenhouse gas emissions by approximately 740,000 tonnes over 20 years
SourceCompany research (stated to be the largest in Japan as of December 2024)
Items this document does not state (7)
Contract ValueOffering priceContract DateAwarding / certifying bodyRegistration number and expiry dateUsage historyImpact on Business Performance

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

To reduce the environmental impact by using a former golf course site without developing new forest land. The project will also contribute to job creation and economic revitalization in the region.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Maniwa Solar Power Plant Begins Operations at Former Golf Course Site, to Supply Environmental Value to LY Corporation for 20 Years | DIGITAL GRID Corporation (350A) timely disclosure | Komori