Strengthening the logistics and sales infrastructure through the construction of the Tomioka No. 2 Warehouse and Showroom
First written in FY2017. 2 of 5 entries say "Restated". Latest entry: FY2018.
No other company in this theme has enough history to compare yet.
- FY2018RestatedAnnual report
「During the fiscal year, the transfer of production of large products to the highly automated Tomioka Plant was completed, and the Tomioka Plant No. 2 Warehouse was also completed. As a result, an integrated mass-production system covering both production and logistics was established at the Tomioka Plant for the supply of large products.」
The completion of the Tomioka No. 2 Warehouse and the completion of the production transfer for large products reconfirmed the establishment of an integrated mass-production system covering production and logistics. - FY2018-Q3AdvancedAnnual report
「Although net sales increased year on year, profit decreased because, in addition to the costs associated with the start of operations at the Tomioka No. 2 Warehouse, material costs increased as a result of higher material prices.」
The filing states that the Tomioka No. 2 Warehouse, whose completion was reported in the previous filing, moved into the operational phase and began generating additional costs. - FY2018-Q2AdvancedAnnual report
「The Tomioka Plant No. 2 Warehouse, which was being constructed to strengthen the logistics system, was completed in October 2017.」
The Tomioka No. 2 Warehouse under construction was completed. This filing does not state that the showroom was completed. - FY2018-Q1RestatedAnnual report
「As part of efforts to build a foundation for the future, the company worked to expand the range of products manufactured at the Tomioka Plant and build a logistics system centered on the plant, including construction of the Tomioka No. 2 Warehouse.」
The Company continues to develop its logistics system and sales infrastructure centered on the Tomioka Plant, including construction of the Tomioka No. 2 Warehouse. - FY2017First statedAnnual report
「To establish a logistics system centered on the Tomioka Plant, the Company is proceeding with construction of the Tomioka No. 2 Warehouse and showroom on the plant premises.」
The Company has newly begun constructing the Tomioka No. 2 Warehouse and showroom to establish a logistics system centered on the Tomioka Plant and develop its showroom facilities.