Increasing inspection capacity with an automated pressure-testing machine for LP gas cylinders
First written in FY2016. 1 of 2 entries say "Softened", first in FY2017. Latest entry: FY2017.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
ガス供給インフラの安全・安定供給維持投資A theme 6 companies write about · 0 as a headwind · 7 as a tailwind
Toell moved to the "Worse" side of this theme in 2017.
The whole theme swung hardest in 2017: 1 of 6 companies on the "Worse" side.
1 other company's latest entry also says "Softened".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2017SoftenedAnnual report
「In the LP gas business, we made capital investments of ¥457 million, including in the construction of gas supply facilities and pressure-inspection equipment for gas cylinders, to ensure a stable supply.」
While investment in pressure-inspection equipment continues, the specific target of a 200% increase in inspection processing capacity and the completion date stated previously are not given in this filing. - FY2016First statedAnnual report
「Additional capacity after completion: 200% increase in inspection processing capacity」
An automated pressure tester will be installed at the Atsugi Plant. Work is scheduled to begin and be completed in August 2016, with inspection processing capacity planned to increase by 200%.