Plan to Construct a 350-Bed Hospital in Bangladesh
First written in FY2016. 2 of 7 entries say "Softened", first in FY2018. Latest entry: FY2023-Q1.
No other company in this theme has enough history to compare yet.
- FY2023-Q1AdvancedAnnual report
「Under these circumstances, projects in the Total Pack Produce business progressed smoothly, and the hospital in Bangladesh reached its grand opening. At the same time, all businesses were affected by higher food, energy and raw material prices.」
The Bangladesh hospital reached its grand opening, progressing beyond the start of medical services in the existing and new buildings to the opening stage. Completion of the overall 650-bed plan was not specified. - FY2022AdvancedAnnual report
「With respect to SHIP AICHI MEDICAL SERVICE, LTD., the original plan is being pursued in light of circumstances following the acceptance of patients with COVID-19, and outpatient medical services at the existing building began on a test-opening basis in November 2019. Medical services commenced in the new 200-bed building in June 2022.」
For the Bangladesh hospital plan, a concrete stage was indicated in which medical services began in the new 200-bed building in June 2022, following the test opening of outpatient services in the existing building. No overall completion date for the plan was specified, and the 650-bed plan was maintained in the facility plan. - FY2021SoftenedAnnual report
「Hospital building; medical equipment; 4,244; 2,369; proceeds from capital increases, etc.; August 2014; August 2021; 650-bed hospital」
The scheduled completion of the Bangladesh hospital plan was deferred from April 2021 to August 2021. The planned capacity of 650 beds was maintained. - FY2020RaisedAnnual report
「650-bed hospital」
The scheduled completion of the Bangladesh hospital plan was changed to April 2021, and the hospital was expanded from the previous plan of 350 beds to 650 beds. Capacity was increased, while the completion date was deferred. - FY2020-Q1RestatedAnnual report
「Meanwhile, initial costs for launching the Osaka Heavy-Ion Radiotherapy Center and the Bangladesh hospital business continued to be recorded, as in the previous fiscal year.」
Initial costs associated with launching the Bangladesh hospital business continued to be recorded, as in the previous fiscal year, indicating that work on the hospital plan remained ongoing. No new completion deadline or completion was stated. - FY2018SoftenedAnnual report
「Hospital building; medical equipment; 4,244; 201; proceeds from capital increases, etc.; August 2014; December 2019; 350-bed hospital」
The scheduled completion of the Bangladesh hospital plan was changed from March 2018 to December 2019. The 350-bed hospital plan was maintained, and cumulative payments were listed at ¥201 million. - FY2016First statedAnnual report
「Hospital building, medical equipment」
Total planned investment: ¥3,400 million; scheduled completion: March 2018; 350-bed hospital. SHIP AICHI MEDICAL SERVICE was listed as scheduled to be established in April 2016.