Revised forecast
Fiscal year ending March 2027 · Second quarter (interim period)Previous forecast published 15 May 2026The bar length represents the relative magnitude of change, based on the item that changed the most in this document. The percentage change shown by the dotted line is calculated from the two reported figures because the company did not provide the rate.
In the Coke business, amid rising market conditions, construction to optimize the production system was completed approximately 1 month ahead of the original schedule, allowing stable production and sales to be maintained. In the Chemical Machinery business, orders for the Tea Meister Mill, a tea-leaf grinding machine for matcha and other teas, remained strong.
| Item | Details |
|---|---|
| Net Sales | ¥45,800 million → ¥48,107 million(+5.0%) |
| Operating profit | ¥800 million → ¥1,103 million(+37.9%) |
| Ordinary income | ¥0 million → ¥438 million |
| Profit attributable to owners of the parent | ¥-800 million → ¥-131 million |
| Net income per share | -2.75 yen and sen → -0.45 yen and sen |
| Fiscal Period Covered | Fiscal year ending March 2027 |
| Period Covered | Second quarter (interim period) |
| Publication date of previous forecast | 15 May 2026 |
| Previous-period results | Actual results for the second quarter of the previous fiscal year (second quarter of the fiscal year ended March 2026): revenue ¥49,680 million, operating profit ¥517 million, ordinary profit ¥413 million, interim net income attributable to owners of the parent -¥487 million, interim earnings per share -¥1.68 |
| Reason for the revision | In the Coke business, amid rising market conditions, construction to optimize the production system was completed approximately 1 month ahead of the original schedule, allowing stable production and sales to be maintained. In the Chemical Machinery business, orders for the Tea Meister Mill, a tea-leaf grinding machine for matcha and other teas, remained strong. |
| Consolidated / non-consolidated | Consolidated |
Items this document does not state (2)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.In the Coke business, amid rising market conditions, construction to optimize the production system was completed approximately 1 month ahead of schedule, allowing stable production and sales to be maintained. In the Chemical Machinery business of the Comprehensive Engineering business, orders for the Tea Meister Mill, a tea-leaf grinding machine for matcha and other teas, remained strong.