Scheduled Completion of 2 Newly Built Condominium Buildings
First written in FY2017-Q1. 9 of 33 entries say "Advanced", first in FY2017-Q3. Latest entry: FY2026.
The whole theme swung hardest in 2022: 2 of 13 companies on the "Worse" side.
7 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「In the real estate business, the 2 newly built condominium projects “トラストレジデンス城内橋 (Karatsu City, Saga Prefecture, 69 units)” and “トラスト白木原レジデンス (Onojo City, Fukuoka Prefecture, 28 units)” were completed. The company focused on sales of “トラストレジデンス伊万里河畔 (Imari City, Saga Prefecture),” “トラスト博多南駅レジデンス (Minami-ku, Fukuoka City)” and “ハレ プアラニ 鴨池 (Kagoshima City, Kagoshima Prefecture),” among others, but the influx of competitors into the sales areas, persistently high construction costs and weaker consumer sentiment due to rising mortgage interest rates caused handovers to fall well below plan, to 68 units, 52 units below plan.」
The 69-unit 城内橋 project and 28-unit 白木原 project were completed, while handovers, including already completed projects, totaled 68 units, 52 units below plan. - 2026-08-10AchievedRevisions to earnings forecastsSuggests it is closing out
「Two newly built condominium buildings, Trust Residence Jonaibashi (Karatsu, Saga Prefecture; 69 units) and Trust Shirakibaru Residence (Onojo, Fukuoka Prefecture; 28 units), were completed.」
The completion of the 2 buildings previously scheduled for completion and delivery was confirmed. - FY2026-H1Presented the scheduled completion and handover of 2 new projects.Annual report
「The company focused on sales of the newly built condominiums “トラストレジデンス城内橋 (Karatsu City, Saga Prefecture)” and “トラスト白木原レジデンス (Onojo City, Fukuoka Prefecture),” scheduled for completion and handover during the fourth quarter.」
In addition to the previously scheduled projects, the company indicated fourth-quarter completion and handover schedules for 2 new projects, “トラストレジデンス城内橋” and “トラスト白木原レジデンス.” - FY2025The scheduled projects were confirmed as completed, but some handover targets were missed.Annual report
「In the real estate business, focusing on sales of already completed condominiums resulted in sell-outs. However, in selling the 3 newly built condominium projects completed during the fiscal year, “トラストレジデンス西鉄久留米駅 (Kurume City, Fukuoka Prefecture, 44 units),” “トラストレジデンス伊万里河畔 (Imari City, Saga Prefecture, 44 units)” and “トラスト博多南駅レジデンス (Minami-ku, Fukuoka City, 23 units),” some handover targets were missed. Including already completed projects, 100 units were handed over, compared with 148 units in the previous fiscal year, resulting in lower revenue and profit year on year.」
The 3 newly built condominium projects were completed, but some handover targets were missed, and handovers totaled only 100 units. - FY2025-H1Presented handover schedules for 2 new projects.Annual report
「The company focused on sales of 2 newly built condominium projects scheduled for completion and handover, “トラストレジデンス伊万里河畔 (Imari City, Saga Prefecture, 44 units; scheduled for handover in April 2025)” and “トラスト博多南駅レジデンス (Minami-ku, Fukuoka City, 23 units; scheduled for handover in May 2025).”」
For 2 new projects with 44 and 23 units, respectively, handover schedules for April and May 2025 and a focus on sales were reported. - FY2024AchievedAnnual report
「In the real estate business, during the fiscal year, 3 newly built condominium projects, “トラスト鳥栖本町ネクサージュ (Tosu City, Saga Prefecture, 54 units),” “トラストレジデンス南里 (Shime Town, Kasuya District, Fukuoka Prefecture, 28 units)” and “トラスト福岡空港駅レジデンス (Shime Town, Kasuya District, Fukuoka Prefecture, 68 units),” were completed.」
The 3 projects, including トラスト福岡空港駅レジデンス, which had been scheduled since the previous fiscal year, were completed. - FY2024-Q3RestatedAnnual report
「In addition, during the fiscal year, completion is scheduled for 1 more newly built condominium project, “トラスト福岡空港駅レジデンス (Shime Town, Kasuya District, Fukuoka Prefecture, 68 units; scheduled for handover in June 2024).”」
The handover schedule for June 2024 continues to be indicated for 1 newly built condominium project with 68 units. - FY2024-Q1Presented the scheduled completion of 1 new project.Annual report
「In addition, during the fiscal year, completion is scheduled for 1 more newly built condominium project, “トラスト福岡空港駅レジデンス (Shime Town, Kasuya District, Fukuoka Prefecture, 68 units; scheduled for handover in June 2024).”」
The company added 1 newly built condominium project with 68 units and indicated a handover schedule for June 2024. - FY2023AchievedAnnual report
「In the real estate business, during the fiscal year, 3 newly built condominium projects, “トラストレジデンス八女 (Yame City, Fukuoka Prefecture, 40 units),” “トラスト春日の杜レジデンス (Kasuga City, Fukuoka Prefecture, 58 units)” and “トラストネクサス生野町 (Shimonoseki City, Yamaguchi Prefecture, 56 units),” were completed. Sales of the already completed “トラストレジデンス基山 (Kiyama Town, Miyaki District, Saga Prefecture)” and “トラストレジデンス三本松 (Hita City, Oita Prefecture)” also continued, bringing total handovers to 161 units.」
The 3 projects, including 生野町, that had been scheduled as of the third quarter were completed during the full year, and 161 units, including units in already completed projects, were handed over. - FY2023-Q3AdvancedAnnual report
「In the real estate business, during the cumulative third quarter of the fiscal year, 2 newly built condominium projects, “トラストレジデンス八女 (Yame City, Fukuoka Prefecture, 40 units)” and “トラスト春日の杜レジデンス (Kasuga City, Fukuoka Prefecture, 58 units),” were completed, and 97 units were handed over, including sales of the already completed “トラストレジデンス基山 (Kiyama Town, Miyaki District, Saga Prefecture)” and “トラストレジデンス三本松 (Hita City, Oita Prefecture).” In addition, during the fiscal year, completion is scheduled for 1 more newly built condominium project, “トラストネクサス生野町 (Shimonoseki City, Yamaguchi Prefecture, 56 units; scheduled for handover in May 2023).”」
The company completed 2 newly built condominium projects and handed over 97 units, while also indicating a May 2023 handover schedule for 1 additional 56-unit newly built condominium project. - FY2023-Q2Presented handover schedules for 2 new projects.Annual report
「In addition, during the fiscal year, completion is scheduled for 2 more newly built condominium projects, “トラスト春日の杜レジデンス (Kasuga City, Fukuoka Prefecture, 58 units; scheduled for handover in February 2023)” and “トラストネクサス生野町 (Shimonoseki City, Yamaguchi Prefecture, 56 units; scheduled for handover in May 2023).”」
The company indicated handovers scheduled for February and May 2023 for 2 additional newly built condominium projects totaling 114 units. - FY2023-Q1AdvancedAnnual report
「In the real estate business, during the first quarter of the fiscal year, 1 newly built condominium project, “トラストレジデンス八女 (Yame City, Fukuoka Prefecture, 40 units),” was completed. Sales of the already completed “トラストレジデンス基山 (Kiyama Town, Miyaki District, Saga Prefecture)” and トラストレジデンス三本松 (Hita City, Oita Prefecture) also continued, and 33 units in total were handed over.」
The 40-unit newly built condominium project “トラストレジデンス八女” was completed, and 33 units, including units in already completed projects, were handed over. - FY2022AdvancedAnnual report
「In the real estate business, during the fiscal year, 3 newly built condominium projects, “トラストレジデンス花立 (Higashi-ku, Kumamoto City, 37 units),” “トラストレジデンス基山 (Kiyama Town, Miyaki District, Saga Prefecture, 60 units)” and “トラストレジデンス三本松 (Hita City, Oita Prefecture, 54 units),” were completed, and 135 units were handed over.」
Progressing from 3 projects and 120 handovers on a cumulative third-quarter basis, 3 projects were completed for the full year and 135 units were handed over. - FY2022-Q3AdvancedAnnual report
「In the real estate business, during the cumulative third quarter of the fiscal year, 3 newly built condominium projects, “トラストレジデンス花立 (Higashi-ku, Kumamoto City, 37 units),” “トラストレジデンス基山 (Kiyama Town, Miyaki District, Saga Prefecture, 60 units)” and “トラストレジデンス三本松 (Hita City, Oita Prefecture, 54 units),” were completed, and 120 units were handed over.」
The number of completed projects increased from 2 as of the second quarter to 3, with 3 projects, including トラストレジデンス三本松, completed and 120 units handed over. - FY2022-Q2AdvancedAnnual report
「In the real estate business, during the cumulative second quarter of the fiscal year, 2 newly built condominium projects, “トラストレジデンス花立 (Higashi-ku, Kumamoto City, 37 units)” and “トラストレジデンス基山 (Kiyama Town, Miyaki District, Saga Prefecture, 60 units),” were completed, and 65 units were handed over.」
Progressing from 1 completed project and 22 handovers as of the first quarter, the company reported the completion of 2 new projects and cumulative handovers of 65 units. - FY2022-Q1AdvancedAnnual report
「In the real estate business, during the first quarter of the fiscal year, 1 newly built condominium project, “トラストレジデンス花立 (Higashi-ku, Kumamoto City, 37 units),” was completed and 22 units were handed over.」
1 newly built condominium project with 37 units was completed, and 22 units were handed over. - FY2021-Q3RestatedAnnual report
「In addition, during the fiscal year, 1 newly built condominium project, “トラスト鳥栖中央レジデンス (Tosu City, Saga Prefecture, 65 units),” will be completed in April 2021.」
The plan for completion in April 2021 continues to be indicated for 1 newly built condominium project with 65 units. - FY2021-Q2ReframedAnnual report
「In addition, during the fiscal year, completion is scheduled for 1 newly built condominium project, “トラスト鳥栖中央レジデンス (Tosu City, Saga Prefecture, 65 units; scheduled for handover in April 2021).”」
The plan was updated from the previous description of completion scheduled for March 2021 to handover scheduled for April 2021 for the 65-unit project. - FY2021-Q1ReframedAnnual report
「In addition, during the fiscal year, completion is scheduled for 1 newly built condominium project, “トラスト鳥栖中央レジデンス (Tosu City, Saga Prefecture, 65 units; scheduled for completion in March 2021).”」
The plan changed from the previous plan for 2 projects to 1 newly built condominium project with 65 units, scheduled for completion in March 2021. - FY2020-Q3AchievedAnnual report
「In the real estate business, during the cumulative third quarter of the fiscal year, 2 newly built condominium projects, “トラスト野間大池公園レジデンス (Minami-ku, Fukuoka City, 33 units)” and “菜花道門コート (Yamaguchi City, Yamaguchi Prefecture, 100 units),” were completed.」
The 2 newly built condominium projects with 33 and 100 units, respectively, that had been scheduled for completion during the fiscal year were completed. - FY2020-Q2RestatedAnnual report
「In addition, during the fiscal year, completion is scheduled for 2 newly built condominium projects, “トラスト野間大池公園レジデンス (Minami-ku, Fukuoka City, 33 units)” and “菜花道門コート (Yamaguchi City, Yamaguchi Prefecture, 100 units).”」
The planned completion of 2 newly built condominium projects with 33 and 100 units, respectively, continues to be indicated. - FY2020-Q1New completion schedule for 2 projects announcedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Noma Oike Park Residence” (Minami Ward, Fukuoka, 33 units, scheduled for completion in January 2020) and the “Dojomonzen Redevelopment Condominium Project” (tentative name) (Yamaguchi, Yamaguchi Prefecture, 100 units, scheduled for completion in February 2020).」
After the completion of the condominium project planned for the previous fiscal year, completion schedules for 2 new projects with 33 and 100 units were announced for January and February 2020. - FY2019-Q3AdvancedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Shingu Chuo Ekimae” (Shingu, Kasuya District, Fukuoka Prefecture, 70 units, completed in April 2019) and “Trust Beppu Ekimae” (Beppu, Oita Prefecture, scheduled for completion in May 2019).」
Of the 2 planned projects, “Trust Shingu Chuo Ekimae” was completed in April 2019, while “Trust Beppu Ekimae” remains scheduled for completion in May 2019. - FY2019-Q2RestatedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Shingu Chuo Ekimae” (Shingu, Kasuya District, Fukuoka Prefecture, 70 units, scheduled for completion in April 2019) and “Trust Beppu Ekimae” (Beppu, Oita Prefecture, 72 units, scheduled for completion in May 2019).」
The scheduled completion of the 2 newly built condominium projects with 70 and 72 units in April and May 2019 continues to be disclosed. - FY2019-Q1New completion schedule for 2 projects announcedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Shingu Chuo Ekimae” (Shingu, Kasuya District, Fukuoka Prefecture, 70 units, April 2019) and “Trust Beppu Ekimae” (Beppu, Oita Prefecture, 72 units, May 2019).」
After the 2 projects from the previous fiscal year were completed, completion schedules for 2 new projects with 70 and 72 units were announced for April and May 2019. - FY2018AchievedAnnual report
「The 2 newly built condominiums “Trust Yamazato Hills” (Okinawa, Okinawa Prefecture, 36 units) and “Trust Nexus Hayatama Park Residence” (Shunan, Yamaguchi Prefecture, 51 units) were completed.」
The 2 newly built condominium projects with 36 and 51 units that had been planned since the previous fiscal year were completed during the fiscal year. - FY2018-Q3RestatedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Yamazato Hills” (Okinawa, Okinawa Prefecture, 36 units, April 2018) and “Trust Nexus Hayatama Park Residence” (Shunan, Yamaguchi Prefecture, 51 units, May 2018).」
The scheduled completion of the 2 projects with 36 and 51 units in April and May 2018 continues to be disclosed. - FY2018-Q2RestatedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Yamazato Hills” (Okinawa, Okinawa Prefecture, 36 units, scheduled for completion in April 2018) and “Trust Nexus Hayatama Park Residence” (Shunan, Yamaguchi Prefecture, 51 units, scheduled for completion in May 2018).」
The scheduled completion of the 2 projects with 36 and 51 units in April and May 2018 continues to be disclosed. - FY2018-Q1New completion plans for 2 projects announcedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Yamazato Hills” (Okinawa, Okinawa Prefecture, 36 units, scheduled for completion in April 2018) and “Trust Nexus Hayatama Park Residence” (Shunan, Yamaguchi Prefecture, 51 units, scheduled for completion in May 2018).」
After the 2 projects planned for the previous fiscal year were completed, completion schedules for 2 new projects with 36 and 51 units were announced for April and May 2018. - FY2017AchievedAnnual report
「The newly built condominiums “Trust Maehara Chuo Nexage II” (Itoshima, Fukuoka Prefecture, 52 units) and “Trust Nexus Shinmukuno II” (Shimonoseki, Yamaguchi Prefecture, 60 units) were completed. The company also focused on sales of the completed properties “Trust Nexus Nagasaki Ocean Court” (Nagasaki, Nagasaki Prefecture), “Trust Nexus Chofu Samurai-machi” (Shimonoseki, Yamaguchi Prefecture), “Trust Mihara Nexage” (Mihara, Hiroshima Prefecture), and “Trust Nexus Ube Kuroishi” (Ube, Yamaguchi Prefecture). Following the delivery of a total of 121 units in newly built and completed properties, revenue was ¥3,075.271 million, down 17.7% year on year, and operating profit was ¥105.419 million, up 13.2%.」
The 2 planned newly built condominium projects were completed during the fiscal year, and a total of 121 units in newly built and completed properties were delivered. - FY2017-Q3AdvancedAnnual report
「In the sales division for condominiums, detached houses and other properties, the newly built condominium “Trust Maehara Chuo Nexage II” (Itoshima, Fukuoka Prefecture) was completed, and 51 of its 52 units were delivered.」
One of the 2 planned newly built condominium projects was completed, and 51 of 52 units were delivered. Deliveries for the other project were scheduled to begin in May 2017. - FY2017-Q2RestatedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled: “Trust Maehara Chuo Nexage II” (Itoshima, Fukuoka Prefecture, 52 units, scheduled for completion in February 2017) and “Trust Nexus Shinmukuno II” (Shimonoseki, Yamaguchi Prefecture, 60 units, scheduled for completion in April 2017).」
The 2 projects, their respective unit counts, and scheduled completion months remain unchanged from the previous disclosure. - FY2017-Q1First statedAnnual report
「In the current consolidated fiscal year, 2 newly built condominium projects are scheduled for completion: “Trust Maehara Chuo Nexage II” (Itoshima, Fukuoka Prefecture, 52 units, scheduled for completion in February 2017) and “Trust Nexus Shinmukuno II” (Shimonoseki, Yamaguchi Prefecture, 60 units, scheduled for completion in April 2017).」
The disclosure specifies 2 projects, the number of units in each, and the scheduled completion month.