Plan to deliver 424 condominiums and 45 detached houses in the fiscal year ending February 2022
First written in FY2021. 1 of 3 entries say "Advanced", first in FY2022-Q3. Latest entry: FY2022.
The whole theme swung hardest in 2018: 1 of 6 companies on the "Worse" side.
2 other companies' latest entry also says "Other".
- FY2022Condominium deliveries above plan, detached-house deliveries below planAnnual report
「In the condominium sales business, the Company's core business and a major contributor to revenue, delivery of 425 units was completed. In the detached-home sales business operated in Yamaguchi Prefecture, delivery of 40 units was completed.」
The plan for the fiscal year ending February 2022 was to deliver 424 condominium units and 45 detached homes. Actual condominium deliveries of 425 units exceeded the plan, while detached-home deliveries of 40 units fell short of it. - FY2022-Q3AdvancedAnnual report
「In addition, the condominium business had already secured contracts for 419 units against full-year planned deliveries of 424 units, representing contract progress of 98.9%.」
For the plan to deliver 424 condominium units in the fiscal year ending February 2022, 419 units had been contracted, representing a progress rate of 98.9%, up from 380 units and 89.7% in the second quarter. - FY2021First statedAnnual report
「For the fiscal year ending February 2022, we plan to deliver 424 condominium units, which make a significant contribution to earnings. We also plan to deliver 45 detached houses, primarily in Yamaguchi Prefecture.」
The company first presented a delivery plan of 424 condominium units and 45 detached houses for the fiscal year ending February 2022.