Plan to deliver 470 condominiums and 60 detached houses in the fiscal year ending February 2021
First written in FY2020. 5 of 6 entries say "Advanced", first in FY2021-Q2. Latest entry: FY2022-Q3.
The whole theme swung hardest in 2018: 1 of 6 companies on the "Worse" side.
3 other companies' latest entry also says "Advanced".
- FY2022-Q3AdvancedAnnual report
「In addition, the condominium business had already secured contracts for 419 units against full-year planned deliveries of 424 units, representing contract progress of 98.9%.」
Against the plan to deliver 424 condominium units in the fiscal year ending February 2022, 419 units had been contracted, representing a 98.9% completion rate. - FY2022-Q2AdvancedAnnual report
「In addition, the condominium business had already secured contracts for 380 units against full-year planned deliveries of 424 units, representing contract progress of 89.7%.」
The number of contracted units against the plan to deliver 424 units in the fiscal year ending February 2022 reached 380, for an 89.7% completion rate, marking progress from the first quarter. - FY2022-Q1AdvancedAnnual report
「In addition, the condominium business had already secured contracts for 332 units against full-year planned deliveries of 424 units, representing contract progress of 78.3%.」
Against the plan to deliver 424 condominium units in the fiscal year ending February 2022, 332 units had been contracted, representing a 78.3% completion rate. - FY2021-Q3AdvancedAnnual report
「In addition, the condominium business had already secured contracts for 435 units against full-year planned deliveries of 470 units, representing contract progress of 92.6%.」
Against the plan to deliver 470 condominium units in the fiscal year ending February 2021, 435 units had been contracted, representing a 92.6% completion rate. - FY2021-Q2AdvancedAnnual report
「In addition, the condominium business had already secured contracts for 339 units against full-year planned deliveries of 470 units, representing contract progress of 72.1%.」
Against the plan to deliver 470 condominium units in the fiscal year ending February 2021, 339 units had been contracted, representing a 72.1% completion rate. - FY2020First statedAnnual report
「For the fiscal year ending February 2021, we plan to deliver 470 condominium units, which make a significant contribution to earnings. We also plan to deliver 60 detached houses, primarily in Yamaguchi Prefecture.」
The company first presented a delivery plan of 470 condominium units and 60 detached houses for the fiscal year ending February 2021.