(Update on Disclosed Matter) Notice Regarding Progress in the Nepal Hydropower Project of a Consolidated Subsidiary and Changes to the Scheduled Timing for Monetization

Due to delays in construction and financing for the Nepal hydroelectric power business, the scheduled monetization date for the 5.5 MW project has been postponed from July 2026 to November 2026, and that for the 13.7 MW project from September 2026 to February 2027.

Worth reading
40Recurring
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Deterioration
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Avoiding a definitive answer
How definitive the wording is.

Progress of the Nepal hydroelectric power business at a consolidated subsidiary and changes to the scheduled monetization timing

Subject Entity

NEPAL HYDRO POWER HOLDINGS Co., Ltd. (NHPH), a consolidated subsidiary of kaihan co.,Ltd., and the business being promoted through NHPH

Target Locations / Products

Hydroelectric power businesses in the Federal Democratic Republic of Nepal: Project No. 1, Dupcheshwor Mahadev Hydro Pvt. Ltd. (5.5 MW); Project No. 4, Betrawati Hydro Electric Company Ltd. (13.7 MW); and Project Nos. 2 and 3

Occurrence14 August 2026 (the change to the scheduled monetization timing was approved at an extraordinary meeting of the Company's Board of Directors)
This disclosure08/14/2026
Cause

Primarily, securing the funds to be borne by the Company for the remaining construction work, grid connection and other requirements necessary before monetization has taken longer than initially expected. Construction progress has also been affected to some extent by unrest in Nepal.

Accounting period in which recognized

Fiscal year ending March 2027 (the impact on consolidated results is currently being reviewed)

Impact on Earnings Forecast

The impact on consolidated results for the fiscal year ending March 2027 is currently under review.

Outlook

The Company will continue negotiating and considering multiple financing options. Subject to completion of the necessary financing by September 2026, the Company aims to monetize the 5.5 MW project in November 2026, while completion and monetization of the 13.7 MW project are scheduled for February 2027.

Planned follow-up disclosure

The Company will promptly provide an update if the timing or method of financing is determined, if any of the assumptions change, or if any matter requiring disclosure arises.

Event that occurred
ItemDetails
Event nameProgress of the Nepal hydroelectric power business at a consolidated subsidiary and changes to the scheduled monetization timing
Date of occurrence14 August 2026 (the change to the scheduled monetization timing was approved at an extraordinary meeting of the Company's Board of Directors)
Subject EntityNEPAL HYDRO POWER HOLDINGS Co., Ltd. (NHPH), a consolidated subsidiary of kaihan co.,Ltd., and the business being promoted through NHPH
Target Locations / ProductsHydroelectric power businesses in the Federal Democratic Republic of Nepal: Project No. 1, Dupcheshwor Mahadev Hydro Pvt. Ltd. (5.5 MW); Project No. 4, Betrawati Hydro Electric Company Ltd. (13.7 MW); and Project Nos. 2 and 3
CausePrimarily, securing the funds to be borne by the Company for the remaining construction work, grid connection and other requirements necessary before monetization has taken longer than initially expected. Construction progress has also been affected to some extent by unrest in Nepal.
Accounting period in which recognizedFiscal year ending March 2027 (the impact on consolidated results is currently being reviewed)
Impact on Earnings ForecastThe impact on consolidated results for the fiscal year ending March 2027 is currently under review.
OutlookThe Company will continue negotiating and considering multiple financing options. Subject to completion of the necessary financing by September 2026, the Company aims to monetize the 5.5 MW project in November 2026, while completion and monetization of the 13.7 MW project are scheduled for February 2027.
Planned follow-up disclosureThe Company will promptly provide an update if the timing or method of financing is determined, if any of the assumptions change, or if any matter requiring disclosure arises.
Items this document does not state (16)
Date recognized / date notice receivedAmount of Impact on Business PerformanceType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionSuspended operationsScheduled resumption dateInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The primary reason is that securing the funds to be borne by the Company for the remaining construction work, grid connection and related requirements has taken longer than expected. Other factors cited include the share price remaining below the level assumed in the initial plan, the issuance of an adverse or disclaimer-of-opinion audit report and other reports, and construction delays caused by past unrest in Nepal.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
(Update on Disclosed Matter) Notice Regarding Progress in the Nepal Hydropower Project of a Consolidated Subsidiary and Changes to the Scheduled Timing for Monetization | kaihan co.,Ltd. (3133) timely disclosure | Komori