Kurabo Industries (3106) · InitiativeRestated

Completion of the Tokushima Biomass Power Plant and Launch of Electricity Sales Operations

First written in FY2017-Q2. 9 of 11 entries say "Restated". Latest entry: FY2021-Q3.

11entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2017-Q2 – FY2017RestatedFY2018-Q2 – FY2021-Q32016: 12017: 420172018: 220182019: 220192020: 120202021: 1
Same theme, other companies
Construction and Start of Operations of Biomass Power PlantsA theme 11 companies write about · 1 as a headwind · 21 as a tailwind

2 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2021-Q3RestatedAnnual report

    「The engineering segment recorded lower revenue as biomass-related facilities performed steadily, but there was less plant-related construction work.」

    The Company has continued to state that biomass-related facilities, including the Tokushima Biomass Power Plant, are performing steadily.
  2. FY2020-Q3RestatedAnnual report

    「The engineering segment recorded higher revenue as the electricity sales business at the Tokushima Biomass Power Plant remained firm and plant-related construction progressed smoothly.」

    The Company has continued to describe the steady performance of the electricity sales business at the Tokushima Biomass Power Plant and smooth progress in plant construction.
  3. FY2020-Q2RestatedAnnual report

    「The engineering segment recorded higher revenue as the electricity sales business at the Tokushima Biomass Power Plant remained firm and plant-related construction progressed smoothly.」

    The Company has continued to state that the electricity sales business at the Tokushima Biomass Power Plant is performing steadily.
  4. FY2020-Q1RestatedAnnual report

    「The engineering segment recorded higher revenue as the electricity sales business at the Tokushima Biomass Power Plant remained firm and plant-related orders at a subsidiary progressed smoothly.」

    The Company has continued to state that the electricity sales business at the Tokushima Biomass Power Plant is performing steadily.
  5. FY2018RestatedAnnual report

    「In the Environmental Mechatronics Business, we will work to expand operations by increasing sales of inspection and measurement equipment in the semiconductor-related and infrastructure fields, operate the Tokushima Biomass Power Plant efficiently, and create new businesses in cooperation with the Technical Research Institute.」

    The Company has continued its business operations, including the continued and more efficient operation of the Tokushima Biomass Power Plant and cooperation with the Technical Research Institute.
  6. FY2018-Q3RestatedAnnual report

    「The engineering segment recorded higher revenue following the completion of a large-scale biomass power plant project, but faced difficult earnings conditions due to higher construction costs.」

    The Company continued to describe increased revenue from the completion of a large-scale biomass power plant project and difficult earnings conditions due to higher construction costs.
  7. FY2018-Q2RestatedAnnual report

    「The engineering segment recorded a substantial increase in revenue following the completion of a large-scale biomass power plant project, but faced difficult earnings conditions due to higher construction costs.」

    The Company continued to describe increased revenue from the completion of a large-scale biomass power plant project and difficult earnings conditions due to higher construction costs.
  8. FY2018-Q1AdvancedAnnual report

    「The engineering segment recorded a substantial increase in revenue following the completion of a large-scale biomass power plant project, but faced difficult earnings conditions due to higher construction costs.」

    A large-scale biomass power plant project was completed, marking specific progress through an expanded revenue base. Meanwhile, earnings remained under pressure from higher construction costs.
  9. FY2017RestatedAnnual report

    「The engineering segment launched the electricity sales business, but remained in a difficult earnings position due to higher construction costs.」

    The launch of the electricity sales business at the Tokushima Biomass Power Plant was also confirmed in the full-year business and performance discussion.
  10. FY2017-Q3RestatedAnnual report

    「The engineering segment expanded its revenue base through the completion of large-scale projects and the launch of the electricity sales business, but remained in a difficult earnings position due to higher construction costs.」

    The expansion of the revenue base through the completion of large-scale projects and the launch of the electricity sales business was described again.
  11. FY2017-Q2First statedAnnual report

    「In addition, the Tokushima Biomass Power Plant, a new business, was completed in July of this year, and began selling electricity.」

    The completion of the Tokushima Biomass Power Plant and the launch of the electricity sales business were first described as specific developments in the new business.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Kurabo Industries yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.