Expansion of the New Hiroshima Plant and Overseas Plants
First written in FY2023. 2 of 4 entries say "Softened", first in FY2025. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026SoftenedAnnual report
「The Company Hiroshima New Factory Construction of new factory 1,349,000 209,746 Proceeds from capital increase, internal funds and borrowings February 2022 June 2027 onward The Company Hiroshima New Factory Production equipment for new factory 480,000 - Internal funds and borrowings June 2026 June 2027 onward TECNISCO (SuZhou) CO.,Ltd. Suzhou Factory Construction of new factory 152,000 - Proceeds from capital increase, internal funds and borrowings October 2023 June 2027 onward」
In addition to construction of the Hiroshima New Factory, the Company added a ¥480,000 thousand production equipment plan, while the expected completion date for both the Hiroshima and Suzhou projects is June 2027 or later, further delaying the planned completion date. - FY2025SoftenedAnnual report
「Company | New Hiroshima plant | Construction of new plant | 1,349,000 | 208,382 | Proceeds from capital increase, internal funds and borrowings | February 2022 | June 2027 onward」
Completion of the new Hiroshima plant is scheduled for June 2027 or later, while construction of the new Suzhou plant and production equipment at the Suzhou plant is planned for June 2026 or later. This has been postponed from the completion timing indicated in the previous filing. - FY2024AdvancedAnnual report
「Company | New Hiroshima plant | Construction of new plant | 1,349,000 | 208,382 | Proceeds from capital increase, internal funds and borrowings | February 2022 | June 2027 onward」
For the new Hiroshima plant, the Group reported ¥208.382 million in payments made to date and indicated a total construction cost of ¥1,349.000 million, with completion scheduled for June 2027 or later. Plans for the new Suzhou plant and new-materials equipment in Singapore also remain in place through June 2025. - FY2023First statedAnnual report
「The funds are scheduled to be allocated to equipment for construction of the Company’s new Hiroshima plant, loans and investments in TECNISCO (SuZhou) CO.,Ltd., and loans and investments in TECNISCO Advanced Materials Pte. Ltd.」
The plans specify ¥1,209.930 million for construction of the new Hiroshima plant, ¥361.000 million for construction and equipment for the new Suzhou plant, and ¥205.000 million for equipment for new materials in Singapore.