Introduction of Production Equipment at Existing Plants
First written in FY2017-Q2. 11 of 29 entries say "Restated". Latest entry: FY2026.
Natori moved to the "Worse" side of this theme in 2025, 1 year after the typical company in this theme (2024).
3 other companies' latest entry also says "Softened".
- FY2026SoftenedAnnual report
「Regarding significant capital expenditures for the fiscal year ending March 2027, the company plans capital investments totaling ¥1,200 million, including the installation of capacity expansion and rationalization equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The company will continue installing capacity expansion and rationalization equipment at each plant and replacing aging equipment, while the planned amount was reduced from the previous ¥1,400 million to ¥1,200 million. - FY2026-H1SoftenedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,400 million, including the installation of capacity expansion and rationalization equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The scope covering the installation of capacity expansion and rationalization equipment at each plant and the replacement of aging equipment was maintained, but the planned capital investment amount was reduced from the previous ¥2,974 million to ¥1,400 million. - FY2025-H1RaisedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥2,974 million, including construction of a core system to strengthen its information systems, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
The planned amount of capital investment, including capacity expansion equipment and the replacement of aging equipment at the plants, increased from the previous ¥1,674 million to ¥2,974 million. - FY2024AdvancedAnnual report
「During the current consolidated fiscal year, the group made capital investments totaling ¥369 million, primarily in production equipment, research and development equipment, and information-related equipment. Of this amount, ¥207 million was invested in expanding production equipment at the company's Saitama Plant, Saitama No. 2 Plant and other facilities, with the aim of enhancing and strengthening its production, quality control and research and development systems.」
The company made capital investments, including the expansion of production equipment at the Saitama Plant, Saitama No. 2 Plant and other facilities, to improve production capacity, quality, productivity and product development capabilities. - FY2024-Q3RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,674 million, including construction of a core system to strengthen its information systems, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
The company continues its ¥1,674 million capital investment plan, including construction of a core system, capacity expansion equipment at each plant, and the replacement of aging equipment. - FY2024-Q2RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,674 million, including construction of a core system to strengthen its information systems, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
The company continues its ¥1,674 million capital investment plan, including construction of a core system, capacity expansion equipment at each plant, and the replacement of aging equipment. - FY2024-Q1SoftenedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,674 million, including construction of a core system to strengthen its information systems, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
The plan covering construction of a core system, capacity expansion equipment at each plant and the replacement of aging equipment continued, but the planned total was reduced from the previous ¥1,874 million to ¥1,674 million. - FY2023SoftenedAnnual report
「Regarding significant capital expenditures for the fiscal year ending March 2024, the company plans capital investments totaling ¥400 million, including rationalization equipment and the replacement of aging equipment at the Saitama Plant and other plants.」
The initiatives involving rationalization equipment and the replacement of aging equipment at each plant will continue, but the planned capital investment amount was reduced from the previous ¥1,874 million to ¥400 million. - FY2023-Q3RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,874 million, including construction of a core system to strengthen its information systems, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
The company continues its ¥1,874 million capital investment plan, including construction of a core system, capacity expansion equipment at each plant, and the replacement of aging equipment. - FY2023-Q2RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,874 million, including construction of a core system to strengthen its information systems, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
The company continues its ¥1,874 million capital investment plan, including construction of a core system and capacity expansion equipment and the replacement of aging equipment at each plant. - FY2023-Q1SoftenedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,874 million, including construction of a core system to strengthen its information systems, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
Construction of a core system was added to the scope of capital investment, while the planned total was reduced from the previous ¥2,690 million to ¥1,874 million. - FY2022-Q3RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥2,690 million, including the acquisition of rental properties, capacity expansion equipment at the Saitama Plant and other plants, and the replacement of aging equipment.」
The company continues its ¥2,690 million capital investment plan, including the acquisition of rental properties, capacity expansion equipment at each plant and the replacement of aging equipment. - FY2022-Q2AdvancedAnnual report
「Cash flow from investing activities was an outflow of ¥1,882 million (an outflow of ¥266 million in the same period). This was mainly due to ¥1,747 million in expenditures for the acquisition of property, plant and equipment, including the acquisition of rental properties and the installation of production equipment at plants.」
In addition to acquiring rental properties, the company installed production equipment at plants and spent ¥1,747 million on the acquisition of property, plant and equipment. - FY2022-Q1SoftenedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,000 million, including capacity expansion equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The initiatives involving capacity expansion equipment at each plant and the replacement of aging equipment were maintained, but the planned amount was reduced from ¥1,100 million to ¥1,000 million. - FY2021-Q3RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,100 million, including capacity expansion equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The company continues its ¥1,100 million capital investment plan, including capacity expansion equipment at each plant and the replacement of aging equipment. - FY2021-Q2RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,100 million, including capacity expansion equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The company continues its ¥1,100 million capital investment plan, including capacity expansion equipment at each plant and the replacement of aging equipment. - FY2021-Q1RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥1,100 million, including capacity expansion equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The company continues its ¥1,100 million capital investment plan, including capacity expansion equipment at each plant and the replacement of aging equipment. - FY2020AdvancedAnnual report
「In the food manufacturing and sales business, the company made capital investments totaling ¥1,884 million. Of this amount, ¥1,758 million was invested in expanding production equipment at the company's Saitama Plant (Kuki, Saitama Prefecture), Saitama No. 2 Plant (Kuki, Saitama Prefecture) and other facilities, with the aim of enhancing and strengthening its production, quality control and research and development systems.」
The company made capital investments, including the expansion of production equipment at the Saitama Plant, Saitama No. 2 Plant and other facilities, to improve production capacity, quality and product development capabilities. - FY2020-Q3RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥2,400 million, including capacity expansion equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The company continues its ¥2,400 million capital investment plan, including capacity expansion equipment at each plant and the replacement of aging equipment. - FY2020-Q2AdvancedAnnual report
「Cash flow from investing activities was an outflow of ¥467 million (an outflow of ¥81 million in the same quarter of the previous year). This was mainly due to ¥291 million in expenditures for the acquisition of property, plant and equipment, including the installation of equipment at plants.」
The company carried out equipment installation at plants and other activities, spending ¥291 million on the acquisition of property, plant and equipment. - FY2020-Q1RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥2,400 million, including capacity expansion equipment at the Saitama Plant and other plants and the replacement of aging equipment.」
The company continues its ¥2,400 million capital investment plan, including capacity expansion equipment at each plant and the replacement of aging equipment. - FY2019AdvancedAnnual report
「In the food manufacturing and sales business, the company made capital investments totaling ¥1,571 million. Of this amount, ¥1,394 million was invested in expanding production equipment at the company's Saitama Plant, Saitama No. 2 Plant and other facilities, with the aim of enhancing and strengthening its production, quality control and research and development systems.」
The company made capital investments, including the expansion of production equipment at the Saitama Plant, Saitama No. 2 Plant and other facilities, to improve production capacity, quality, productivity and product development capabilities. - FY2019-Q3RestatedAnnual report
「Regarding significant capital expenditures, the company plans capital investments totaling ¥3,000 million, including capacity expansion equipment and manufacturing-line rationalization at the Saitama Plant and other plants, as well as the replacement of aging equipment.」
The company continues its capital investment plan, including capacity expansion equipment at each plant, manufacturing-line rationalization, and the replacement of aging equipment. - FY2018AdvancedAnnual report
「During the current consolidated fiscal year, the group made capital investments totaling ¥3,411 million, primarily in production equipment, research and development equipment, and information-related equipment. Of this amount, ¥2,754 million was invested in expanding production equipment at the company's Saitama Plant, the Saitama No. 2 Plant and other facilities.」
The company made capital investments, including ¥2,754 million for expanding production equipment at the Saitama Plant, Saitama No. 2 Plant and other facilities. Equipment installation also progressed as the Saitama No. 2 Plant began operations. - FY2018-Q3AdvancedAnnual report
「Although cash and deposits declined, total assets increased mainly because notes and accounts receivable increased, lease assets increased following the installation of production equipment at the newly built Saitama No. 2 Plant, and raw material inventories increased as a result of soaring prices for Japanese flying squid, among other factors.」
The company stated that the installation of production equipment continued at the newly built Saitama No. 2 Plant, increasing lease assets. - FY2018-Q2AdvancedAnnual report
「Cash flow from investing activities was an outflow of ¥2,049 million (an outflow of ¥1,613 million in the same quarter of the previous year). This was mainly due to ¥2,011 million in expenditures for the acquisition of property, plant and equipment, including construction costs for the Saitama No. 2 Plant.」
The company spent ¥2,011 million on the acquisition of property, plant and equipment, including construction costs for the Saitama No. 2 Plant. Capital investment, including the installation of production equipment, progressed. - FY2018-Q1AdvancedAnnual report
「Total assets increased, mainly because lease assets increased following the installation of production equipment at the newly built Saitama No. 2 Plant and raw material inventories increased as a result of soaring prices for Japanese flying squid, among other factors.」
The installation of production equipment progressed at the completed Saitama No. 2 Plant. The company stated that the installation increased lease assets. - FY2017AdvancedAnnual report
「In the food manufacturing and sales business, the company made capital investments totaling ¥5,236 million. Of this amount, ¥4,348 million was invested in constructing the company's Saitama No. 2 Plant (Kuki, Saitama Prefecture), and ¥758 million in expanding production equipment at the company's Saitama Plant (Kuki, Saitama Prefecture) and other facilities, with the aim of enhancing and strengthening its production, quality control and research and development systems.」
In addition to constructing the Saitama No. 2 Plant, the company proceeded with the expansion and renewal of production equipment at existing plants and other facilities, investing ¥5,236 million in the food manufacturing and sales business. - FY2017-Q2First statedAnnual report
「The status of each cash flow during the cumulative second quarter of the current consolidated fiscal year and the factors affecting them are as follows. Cash flow from investing activities was an outflow of ¥1,613 million (an outflow of ¥107 million in the same quarter of the previous year). This was mainly due to ¥1,596 million in expenditures for the acquisition of property, plant and equipment, including partial payment of construction costs for the new plant and the installation of production equipment at existing plants.」
The company installed production equipment at existing plants and spent ¥1,596 million on the acquisition of property, plant and equipment.