Expanding production capacity in the Kansai region through the new Kansai plant
First written in FY2016. 5 of 10 entries say "Advanced", first in FY2017-Q1. Latest entry: FY2020-Q2.
No other company in this theme has enough history to compare yet.
- FY2020-Q2AchievedAnnual report
「In production, the New Kansai Plant in Nishiyodogawa-ku, Osaka, began operations smoothly in July.」
The New Kansai Plant began operations in July 2019, bringing the construction and start-up plan to the completion stage. Investment in the main equipment was ¥6,524 million. - FY2020-Q1AdvancedAnnual report
「In production, we advanced preparations for the New Kansai Plant in Nishiyodogawa-ku, Osaka, to begin operations in July, including strengthening the HACCP-based hygiene management system and improving productivity through the use of the latest equipment.」
The New Kansai Plant progressed to the preparation stage for its July start of operations, including preparations for hygiene management and equipment. - FY2019AdvancedAnnual report
「In addition to the above, construction in progress for the New Kansai Plant in Nishiyodogawa-ku, Osaka increased by ¥3,265 million. The New Kansai Plant in Nishiyodogawa-ku, Osaka, is scheduled to begin operations in July 2019.」
Construction in progress for the New Kansai Plant increased by ¥3,265 million, and operations were scheduled to begin in July 2019. The amount already paid under the equipment plan was ¥4,426 million, and maximum production capacity after completion was expected to be 1.8 times. - FY2019-Q3SoftenedAnnual report
「The plan as of the end of the previous consolidated fiscal year called for completion in March 2019, but the construction schedule is expected to be delayed due to the impact of natural disasters, including the Northern Osaka Earthquake, the torrential rains in western Japan and Typhoon No. 21, and has therefore been changed as described above.」
The planned completion date for the New Kansai Plant was changed from March 2019 to July 2019. Total planned investment of ¥6 billion, ¥4,063 million already paid, and maximum production capacity of 1.8 times after completion remain unchanged. - FY2018RestatedAnnual report
「Reporting company; New Kansai Plant (tentative name); Nishiyodogawa-ku, Osaka; land, buildings, production equipment, etc.; 6,000; 1,424; borrowings; November 2016; March 2019; 1.8 times」
The plan for the New Kansai Plant continued to call for total investment of ¥6 billion, ¥1,424 million already paid, completion in March 2019, and maximum production capacity of 1.8 times after completion. - FY2017SoftenedAnnual report
「The plan as of the end of the previous consolidated fiscal year called for completion in November 2017, but it has been changed as described above due to a review of the design and construction schedule, among other factors.」
The planned completion date for the New Kansai Plant was changed from November 2017 to March 2019. The disclosed plan continues to include total planned investment of ¥6 billion, ¥1,151 million already paid, and maximum production capacity of 1.8 times after completion. - FY2017-Q3AdvancedAnnual report
「Total assets increased by ¥1,303 million from the end of the previous consolidated fiscal year to ¥21,107 million, mainly due to an increase in property, plant and equipment resulting from the acquisition of land for construction of the new plant.」
The acquisition of construction land for what appears to be the New Kansai Plant was reflected in the financial position, and the construction plan progressed to the land acquisition stage. - FY2017-Q2AdvancedAnnual report
「In connection with the construction of the New Kansai Plant (tentative name; the same applies below), the Company resolved at a Board of Directors meeting held on 20 July 2016 to enter into a syndicated loan agreement for the stable procurement of construction funds, and entered into the syndicated loan agreement on 31 August 2016. (1) Facility amount: ¥6 billion」
Following the resolution to enter into the agreement in the previous quarter, the Company actually entered into the ¥6 billion syndicated loan agreement on 31 August 2016. - FY2017-Q1AdvancedAnnual report
「In connection with the construction of the New Kansai Plant (tentative name; the same applies below), the Company resolved at a Board of Directors meeting held on 20 July 2016 to enter into a syndicated loan agreement for the stable procurement of construction funds. (1) Facility amount: ¥6 billion (2) Use of funds: Construction of the New Kansai Plant」
Resolved to enter into a ¥6 billion syndicated loan agreement for construction of the New Kansai Plant. The project progressed to the stage of securing construction funding. - FY2016First statedAnnual report
「This is intended to increase production capacity in the Kansai region and further expand sales.」
For the New Kansai Plant, the plan called for total investment of approximately ¥6 billion, construction to begin in November 2016, production to start in November 2017, and production capacity of 450,000 meals per day. The planned increase in capacity after completion was stated as 1.8 times.