Expansion and renovation plans for the Hiroshima and Nagoya plants
First written in FY2019. 1 of 4 entries say "Softened", first in FY2020-Q3. Latest entry: FY2021-Q2.
No other company in this theme has enough history to compare yet.
- FY2021-Q2AchievedAnnual report
「During the six-month period ended 30 September 2020, the following planned major capital expenditure projects from the end of the previous consolidated fiscal year were completed: filing company; Nagoya Plant; Yatomi, Aichi Prefecture; plant expansion and renovation; 840; September 2020」
The Nagoya Plant expansion and renovation progressed from the plan at the end of the previous fiscal year and was completed in September 2020. The investment was stated as ¥840 million. - FY2020Progress on the expansion was reported, and the scheduled completion of the Nagoya Plant was postponed.Annual report
「The plan at the end of the previous consolidated fiscal year was scheduled for completion in March 2020, but it has been changed as described above following a review of the construction period and other factors.」
For the Nagoya Plant expansion and renovation plan, the scheduled completion date was changed from March 2020 to August 2020. The planned investment was ¥800 million, of which ¥779 million had already been paid. The report also mentioned increased production capacity from the expansion of the Hiroshima and Nagoya plants. - FY2020-Q3SoftenedAnnual report
「The plan at the end of the previous consolidated fiscal year was scheduled for completion in November 2019, but it has been changed as described above following a review of the construction period and other factors.」
For the Hiroshima Plant expansion and renovation plan, the scheduled completion date was changed from November 2019 to February 2020. The planned total investment was ¥760 million, of which ¥376 million had already been paid. - FY2019First statedAnnual report
「Filing company; Hiroshima Plant; Onomichi, Hiroshima Prefecture; plant expansion and renovation; 760; 154; borrowings; October 2018; November 2019; filing company; Nagoya Plant; Yatomi, Aichi Prefecture; plant expansion and renovation; 800; 29; borrowings; March 2019; March 2020」
For the following year’s capital expenditure plan, the company first explicitly stated its plan to invest ¥760 million in the Hiroshima Plant and ¥800 million in the Nagoya Plant for plant expansion and renovation. The increase in capacity after completion was considered difficult to calculate.