New Niigata Plant Wastewater Treatment Facility and Production Capacity ExpansionA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2021AdvancedAnnual report
「The main capital expenditures were ¥24.1 million for equipment to improve production efficiency and reduce losses, and ¥63 million for a wastewater treatment facility at the Niigata Plant.」
The company made ¥63 million in capital expenditures during the fiscal year for the wastewater treatment facility at the Niigata Plant that had been planned in the previous fiscal year. - FY2020First statedAnnual report
「Niigata Plant Wastewater treatment facility 63 42 Internal funds December 2019 June 2020 20% increase in production capacity」
A wastewater treatment facility was newly constructed at the Niigata Plant at a total cost of ¥63 million, with completion and a 20% increase in production capacity scheduled for June 2020. The amount already paid was ¥42 million, and the project was planned to be funded with internal resources.