Komori
Sato Foods Industries (2814) · RiskRestated

Phase Three Construction at the Third Plant Delayed, Restart Date Undetermined

First written in FY2016. 20 of 21 entries say "Restated". Latest entry: FY2026.

21entries
11years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2017 – FY20262016: 120162017: 120172018: 020182019: 220192020: 320202021: 420212022: 420222023: 320232024: 020242025: 220252026: 12026
Same theme, other companies
Risk of delays and cost overruns in capital investment and systems developmentA theme 12 companies write about · 12 as a headwind · 0 as a tailwind

The whole theme swung hardest in 2026: 1 of 6 companies on the "Worse" side.

3 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の計画再検討及び工事再開時期未定との説明を再掲している。
  2. FY2026-H1RestatedAnnual report

    「During the interim accounting period, there were no material changes to the emergence of major risks that management recognizes as potentially having a material impact on the Company's financial position, operating results or cash flows, or to the matters described under 'Business and Other Risks' in the annual securities report for the previous fiscal year.」

    第三工場第三期工事の延期・再開時期未定を含む主要なリスクについて、発生又は重要な変更がないとしている。
  3. FY2025RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の計画再検討及び工事再開時期未定との説明を再掲している。
  4. FY2024-Q2RestatedAnnual report

    「During the cumulative second quarter period, there were no material changes in the occurrence of major risks that management recognizes could materially affect the company's financial position, operating results or cash flows, among the matters concerning the business and financial condition described in this quarterly securities report, or in the business and other risks described in the securities report for the previous fiscal year.」

    前事業年度の有価証券報告書に記載した事業等のリスクについて、主要なリスクの発生又は重要な変更がないとしている。
  5. FY2024-Q1RestatedAnnual report

    「During the cumulative first quarter, there were no new occurrences of the major risks that management recognizes as potentially having a material impact on the company’s financial position, operating results or cash flows, among the matters concerning the business and accounting conditions described in this quarterly report, nor were there any material changes to the risks described in the “Business and Other Risks” section of the annual securities report for the previous fiscal year.」

    前事業年度記載の事業等のリスクについて、主要なリスクの発生又は重要な変更がないとしている。
  6. FY2023RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の計画再検討及び工事再開時期未定との説明を再掲している。
  7. FY2023-Q2RestatedAnnual report

    「During the cumulative second quarter period, there were no material changes in the occurrence of major risks that management recognizes could materially affect the company's financial position, operating results or cash flows, among the matters concerning the business and financial condition described in this quarterly securities report, or in the business and other risks described in the securities report for the previous fiscal year.」

    第三工場第三期工事の再開時期未定を含む前事業年度記載の主要なリスクについて、発生又は重要な変更がないとしている。
  8. FY2023-Q1RestatedAnnual report

    「During the cumulative first quarter, there were no new occurrences of the major risks that management recognizes as potentially having a material impact on the company’s financial position, operating results or cash flows, among the matters concerning the business and accounting conditions described in this quarterly report, nor were there any material changes to the risks described in the “Business and Other Risks” section of the annual securities report for the previous fiscal year.」

    前事業年度の有価証券報告書に記載した事業等のリスクについて、主要なリスクの発生又は重要な変更がないとしている。
  9. FY2022RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の計画再検討及び工事再開時期未定との説明を再掲している。
  10. FY2022-Q3RestatedAnnual report

    「During the cumulative third quarter period, there were no occurrences of the major risks that management recognizes could have a material impact on the financial position, operating results or cash flows of the company, nor any material changes to the "Business and Other Risks" described in the annual securities report for the previous fiscal year, among the matters concerning the business and financial condition described in this quarterly report.」

    第三工場第三期工事の再開時期未定を含む主要なリスクについて、発生又は重要な変更がないとしている。
  11. FY2022-Q2RestatedAnnual report

    「During the cumulative second quarter period, there were no material changes in the occurrence of major risks that management recognizes could materially affect the company's financial position, operating results or cash flows, among the matters concerning the business and financial condition described in this quarterly securities report, or in the business and other risks described in the securities report for the previous fiscal year.」

    主要なリスクの発生又は前事業年度の有価証券報告書に記載した事業等のリスクについて、重要な変更がないとしている。
  12. FY2022-Q1RestatedAnnual report

    「During the cumulative first quarter, there were no new occurrences of the major risks that management recognizes as potentially having a material impact on the company’s financial position, operating results or cash flows, among the matters concerning the business and accounting conditions described in this quarterly report, nor were there any material changes to the risks described in the “Business and Other Risks” section of the annual securities report for the previous fiscal year.」

    主要なリスクの発生又は前事業年度の有価証券報告書に記載した事業等のリスクについて、重要な変更がないとしている。
  13. FY2021RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の計画再検討及び工事再開時期未定との説明を再掲している。
  14. FY2021-Q3RestatedAnnual report

    「During the cumulative third quarter period, there were no occurrences of the major risks that management recognizes could have a material impact on the financial position, operating results or cash flows of the company, nor any material changes to the "Business and Other Risks" described in the annual securities report for the previous fiscal year, among the matters concerning the business and financial condition described in this quarterly report.」

    前事業年度の有価証券報告書に記載した事業等のリスクについて、重要な変更がないとの説明を再掲している。
  15. FY2021-Q2RestatedAnnual report

    「During the cumulative second quarter period, there were no material changes in the occurrence of major risks that management recognizes could materially affect the company's financial position, operating results or cash flows, among the matters concerning the business and financial condition described in this quarterly securities report, or in the business and other risks described in the securities report for the previous fiscal year.」

    主要なリスクの発生又は前事業年度の有価証券報告書に記載した事業等のリスクについて、重要な変更がないとの説明を再掲している。
  16. FY2020RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の計画再検討及び工事再開時期未定との説明を再掲している。
  17. FY2020-Q3RestatedAnnual report

    「During the cumulative third quarter of the current fiscal year, there were no occurrences of matters concerning the business situation, accounting situation or other matters described in the quarterly report that could have a material impact on investors’ decisions, and no material changes to the “Business and Other Risks” described in the annual securities report for the previous fiscal year.」

    前事業年度の有価証券報告書に記載した事業等のリスクについて、重要な変更がないとの説明を再掲している。
  18. FY2020-Q2RestatedAnnual report

    「During the cumulative second quarter of the current fiscal year, there were no occurrences of matters concerning the business situation, accounting situation or other matters described in the quarterly report that could have a material impact on investors’ decisions, and no material changes to the “Business and Other Risks” described in the annual securities report for the previous fiscal year.」

    前事業年度の有価証券報告書に記載した事業等のリスクについて、重要な変更がないとの説明を再掲している。
  19. FY2019RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の計画再検討及び工事再開時期未定との説明を再掲している。
  20. FY2017RestatedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    第三工場第三期工事の再開時期がなお未定であるとの説明を再掲している。
  21. FY2016MaterialisedAnnual report

    「We are reviewing the Phase Three construction plan. The date for resuming construction has not yet been determined.」

    The company has already announced a postponement of Phase Three construction at the Third Plant and states that the restart date remains undetermined.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
Sato Foods Industries's next results are scheduled for 2026-11-06. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.