Expanding Production Capacity Through Phase Three of Construction at the Third Plant
First written in FY2016. 8 of 9 entries say "Restated". Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026RestatedAnnual report
「第三工場(愛知県春日井市)第三期工事(製造設備)について、投資予定額1,699,000千円、既支払額84,361千円、着手年月2010年12月、未定、完成後の増加能力50%増加。」
第三工場第三期工事について、投資予定額、既支払額、完了予定未定及び完成後の増加能力50%という計画を再掲している。 - FY2025RestatedAnnual report
「Regarding Phase 3 construction at the Third Plant in Kasugai, Aichi Prefecture, for manufacturing equipment: planned investment of ¥1,699 million, amount already paid of ¥84.361 million, construction start date of December 2010, completion date undecided, and a 50% increase in capacity after completion.」
第三工場第三期工事について、投資予定額、既支払額、完了予定年月未定及び完成後の増加能力50%という計画を引き続き記載している。 - FY2023RestatedAnnual report
「Regarding Phase 3 construction at the Third Plant in Kasugai, Aichi Prefecture, for manufacturing equipment: planned investment of ¥1,699 million, amount already paid of ¥84.361 million, construction start date of December 2010, completion date undecided, and a 50% increase in capacity after completion.」
第三工場第三期工事について、投資額、既支払額、増加能力及び完了予定年月未定という計画を引き続き記載している。 - FY2022RestatedAnnual report
「Regarding Phase 3 construction at the Third Plant in Kasugai, Aichi Prefecture, for manufacturing equipment: planned investment of ¥1,699 million, amount already paid of ¥84.361 million, construction start date of December 2010, completion date undecided, and a 50% increase in capacity after completion.」
第三工場第三期工事について、投資額、既支払額、増加能力及び完了予定年月未定という計画を引き続き記載している。 - FY2021RestatedAnnual report
「Regarding Phase 3 construction at the Third Plant in Kasugai, Aichi Prefecture, for manufacturing equipment: planned investment of ¥1,699 million, amount already paid of ¥84.361 million, construction start date of December 2010, completion date undecided, and a 50% increase in capacity after completion.」
第三工場第三期工事について、投資額、既支払額、増加能力及び完了予定年月未定という計画を引き続き記載している。 - FY2020RestatedAnnual report
「Regarding Phase 3 construction at the Third Plant in Kasugai, Aichi Prefecture, for manufacturing equipment: planned investment of ¥1,699 million, amount already paid of ¥84.361 million, construction start date of December 2010, completion date undecided, and a 50% increase in capacity after completion.」
第三工場第三期工事について、投資額、既支払額、増加能力及び完了予定年月未定という計画を引き続き記載している。 - FY2019RestatedAnnual report
「Regarding Phase 3 construction at the Third Plant in Kasugai, Aichi Prefecture, for manufacturing equipment: planned investment of ¥1,699 million, amount already paid of ¥84.361 million, construction start date of December 2010, completion date undecided, and a 50% increase in capacity after completion.」
The company continues to disclose the plan for Phase 3 construction at the Third Plant, including the investment amount, expected capacity increase and undecided completion date. - FY2017RestatedAnnual report
「Regarding Phase Three of construction at the Third Plant in Kasugai, Aichi Prefecture, for production equipment: planned investment of ¥1,699,000 thousand, amount paid to date of ¥84,361 thousand, construction commencement in December 2010, completion date undetermined, and a 50% increase in capacity after completion.」
第三工場第三期工事について、投資額・増加能力・完了予定年月未定という従来計画を引き続き記載している。 - FY2016First statedAnnual report
「Regarding Phase Three of construction at the Third Plant in Kasugai, Aichi Prefecture, for production equipment: planned investment of ¥1,699,000 thousand, amount paid to date of ¥84,361 thousand, construction commencement in December 2010, completion date undetermined, and a 50% increase in capacity after completion.」
The project is planned as Phase Three construction financed with internal funds.