Improving Management Resource Efficiency and Strengthening the Financial Position through the Transfer of Idle Fixed Assets
First written in FY2023-Q1. 1 of 4 entries say "Advanced", first in FY2023-Q2. Latest entry: FY2023.
16 other companies' latest entry also says "Achieved".
- FY2023AchievedAnnual report
「Cash provided by investing activities was ¥45 million. The main component of cash inflows was ¥170 million from the sale of property, plant and equipment.」
Regarding the disposal of fixed assets, which had been delayed from the previous schedule, the company recorded ¥170 million in proceeds from the sale of property, plant and equipment during the fiscal year, indicating that the disposal was completed. - FY2023-Q3SoftenedAnnual report
「At a board of directors meeting held on 12 December 2022, the company resolved to dispose of fixed assets as described below.」
For the disposal of fixed assets, the company presented a new schedule with the agreement to be signed in late January 2023 and handover in late April 2023, later than the previous handover schedule of October 2022. - FY2023-Q2AdvancedAnnual report
「At a board of directors meeting held on 13 June 2022, the company resolved to dispose of fixed assets as described below and, based on that resolution, entered into a disposal agreement on 30 June 2022.」
Regarding the disposal plan for idle fixed assets, the company entered into a disposal agreement on 30 June. Handover was scheduled for 20 October, with a gain on disposal of approximately ¥36.87 million expected. - FY2023-Q1First statedAnnual report
「The company will dispose of fixed assets to improve the efficiency of management resources and strengthen the group’s financial position. Gain on disposal: approximately ¥36.87 million Handover date of disposed assets: 20 October 2022 (scheduled)」
The company disclosed a plan to dispose of idle land and buildings to improve the efficiency of management resources and strengthen its financial position. The gain on disposal was expected to be approximately ¥36.87 million, with handover scheduled for 20 October 2022.