Changes to the Plan for Introducing Measuring Instruments and Evaluation Equipment at the Engineering Center

First written in FY2023-Q2. 2 of 4 entries say "Advanced", first in FY2023-Q3. Latest entry: FY2024-Q1.

4entries
2years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2023-Q2AdvancedFY2023-Q3 – FY2024-Q12022: 120222023: 32023
Same theme, other companies
業務用プリンタ・防災倉庫等の設備投資計画変更A theme 4 companies write about · 0 as a headwind · 3 as a tailwind

0 other companies' latest entry also says "Achieved".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2024-Q1AchievedAnnual report

    「Reporting company Engineering Center (Tsuzuki-ku, Yokohama) Semiconductor and electronic device business Measuring equipment and evaluation equipment 55 Internal funds May 2023」

    The plan to install measuring and evaluation equipment at the Engineering Center was completed, with total investment of ¥55 million, in May 2023.
  2. FY2023AdvancedAnnual report

    「Reporting company Engineering Center (Tsuzuki-ku, Yokohama) Semiconductor and electronic device business Measuring equipment and evaluation equipment 55 54 Internal funds August 2022 May 2023」

    Under the plan to install measuring and evaluation equipment at the Engineering Center, ¥54 million of the planned investment of ¥55 million had been paid, bringing the project close to its scheduled completion in May 2023. The planned investment was also changed from the previous amount of ¥66 million.
  3. FY2023-Q3AdvancedAnnual report

    「Measuring equipment and evaluation equipment 66 (Note 1) 22 Internal funds August 2022 (Note 2) May 2023 (Note 2)」

    Under the plan to install measuring and evaluation equipment at the Engineering Center, ¥22 million of the planned investment of ¥66 million had been paid and recorded, indicating progress in executing the plan. The scheduled completion date remained May 2023.
  4. FY2023-Q2First statedAnnual report

    「Reporting company Engineering Center (Tsuzuki-ku, Yokohama) Semiconductor and electronic device business Measuring equipment and evaluation equipment 66 (Note 1) — Internal funds August 2022 (Note 2) May 2023 (Note 2)」

    For the plan to install measuring and evaluation equipment at the Engineering Center using internal funds, the planned investment was changed to ¥66 million following a detailed review of the development work, while the start date was changed to August 2022 and the scheduled completion date to May 2023 due to delays in the development schedule.
Moved together

"Recovery in results driven by the semiconductor and electronic device business" moved the same way as this thread, in the same document, in 3 of its 4 moves.

33222★12345
  1. ★This thread
  2. 1Recovery in results driven by the semiconductor and electronic device business3×
  3. 2Risks to Business Activity, Demand and Financing from COVID-193×
  4. 3Medium-Term ROE Target of 10% and Improvement in the Debt-to-Equity Ratio and Equity Ratio2×
  5. 4Expansion of product and maintenance capabilities in data centers, cloud computing and security2×
  6. 5Financing Through Internal Funds, Bank Borrowings and Trade Receivables Securitization, and Strengthening Financial Soundness2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Tokyo Electron Device Limited's next results are scheduled for 2026-10-28. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.