Construction of a New Plant in Ono City
First written in FY2022. 3 of 6 entries say "Advanced", first in 2026-06-02. Latest entry: 2026-08-14.
S.Ishimitsu& moved to the "Worse" side of this theme in 2023.
0 other companies' latest entry also says "Advanced".
- 2026-08-14AdvancedM&A and Subsidiary Changes
「The fixed assets listed below, held by a consolidated subsidiary, will be transferred to fund the construction of the new plant announced in the 23 May 2025 notice entitled "(Progress of Disclosed Matters) Notice Regarding the Construction of a New Plant."」
Specific funding arrangements for the new plant were disclosed: idle assets held by a consolidated subsidiary will be transferred, with the proceeds applied to construction funding. - FY2026AdvancedAnnual report
「アライドコーヒーロースターズ㈱ Ono Plant (Ono City, Hyogo Prefecture) New plant construction 4,800,000 871,489 Internal funds, subsidies and borrowings March 2022 December 2026 Annual roasting capacity of 8 thousand tonnes」
Construction of the Ono Plant has begun. The planned investment is ¥4.8 billion, of which ¥871.489 million has been paid, with completion scheduled for December 2026 and planned annual roasting capacity of 8 thousand tonnes. Capacity has been revised from the previous plan of 10 thousand tonnes per year. - 2026-06-02AdvancedGeneral Meetings of Shareholders
「Regarding the construction of a new plant by アライドコーヒーロースターズ㈱, a consolidated subsidiary, the investment amount is ¥4,800 million. This investment was selected for and received a grant decision under the Ministry of Economy, Trade and Industry's "Large-Scale Growth Investment Subsidy Program for Labor-Saving Measures to Support Wage Increases at Medium-Sized and Small Enterprises (Second Application Round)," and a subsidy of approximately ¥1,500 million is expected to be provided. (Construction start: October 2025; completion scheduled for December 2026)」
The previously undecided new plant was given specific details, including an investment amount of ¥4,800 million, construction start date, scheduled completion date and expected subsidy amount. - FY2024SoftenedAnnual report
「The investment amount was initially expected to be ¥2,200,000 thousand, but is now undetermined due to revisions to the equipment specifications and construction plan, as well as the impact of soaring construction material costs. Completion was initially scheduled for April 2024, but the scheduled completion month is now undetermined due to revisions to the construction plan and other factors.」
For the new Ono City plant, both the investment amount and scheduled completion month became undetermined, with further details receding from the previous April 2025 schedule. The plan for annual roasting capacity of 10 thousand tonnes is still stated. - FY2023SoftenedAnnual report
「The investment amount was initially expected to be ¥2,200,000 thousand, but is now undetermined due to revisions to the equipment specifications and construction plan, as well as the impact of soaring construction material costs. Completion was initially scheduled for April 2024, but the scheduled completion date has been postponed to April 2025 due to revisions to the construction plan and other factors.」
For the new Ono City plant, the investment amount was changed from the initial ¥2.2 billion and the scheduled completion in April 2024 to an undetermined investment amount and completion postponed to April 2025. The planned annual roasting capacity of 10 thousand tonnes remains unchanged. - FY2022First statedAnnual report
「Reporting company Facilities leased to an affiliated company (Ono City) — New plant construction 2,200,000 — Internal funds and borrowings March 2022 April 2024 Annual roasting capacity of 10 thousand tonnes」
The Company planned to construct a new plant in Ono City at a total cost of ¥2.2 billion, with construction starting in March 2022 and completion scheduled for April 2024. Annual roasting capacity after completion was expected to be 10 thousand tonnes.