Grid Connection Risks in the Grid-Scale Battery Storage Business
First written in FY2025-H1. 1 of 2 entries say "Worsened", first in FY2026-H1. Latest entry: FY2026-H1.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Risk of delays and capacity constraints in grid connection for grid-scale battery storageA theme 3 companies write about · 3 as a headwind · 0 as a tailwind
J-Holdings Corp. moved to the "Worse" side of this theme in 2026.
0 other companies' latest entry also says "Worsened".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2026-H1WorsenedAnnual report
「一方、急激な参入事業者の増加により、電力系統への連携が完了するまでの期間の長期化や、電力市場の競争環境が将来的に厳しくなる可能性などの課題も生じております。」
系統用蓄電池事業への参入拡大に関連して、急速な参入事業者の増加により電力系統への連系完了までの期間が長期化する課題を明示している。既存の系統接続に関するスケジュール遅延・コスト増加リスクに対応する記載である。 - FY2025-H1First statedAnnual report
「蓄電池の設置には送配電事業者との系統接続協議が必要となり、受電条件や接続可能容量の制限、接続可否判断の長期化などにより開発スケジュールの遅延やコスト増加が生じた場合には、当社事業計画に影響を及ぼす可能性があります。」
蓄電池設置に必要な系統接続協議について、受電条件・接続可能容量の制限や接続可否判断の長期化が、開発スケジュールの遅延やコスト増加につながる可能性を開示している。