Contract award to a subsidiary for the “Yamagata Main Line Voltage Increase Extension Tower Construction”
ETSライン株式会社 (the Company's consolidated subsidiary)
Yamagata Main Line Voltage Increase Extension Tower Construction (Part 2), Construction Section 2, Sakata, Yamagata Prefecture, and other locations. Seventeen of the 112 new towers, covering approximately 10.1 km of 500 kV transmission lines
The portion completed in September 2026 has already been reflected in the earnings forecast announced on 7 August 2026. The company will promptly disclose any revisions if it becomes necessary to revise the forecast figures.
The construction period is from September 2026 to March 2033. Operations are scheduled to commence in October 2033. The company will promptly disclose any revisions if it becomes necessary to revise the forecast figures.
The company will promptly disclose any revisions if it becomes necessary to revise the forecast figures. The timing for finalising the contract value is Not disclosed.
| Item | Details |
|---|---|
| Event name | Contract award to a subsidiary for the “Yamagata Main Line Voltage Increase Extension Tower Construction” |
| Date of occurrence | September 2026 (construction commencement; specific date: Not disclosed) |
| Subject Entity | ETSライン株式会社 (the Company's consolidated subsidiary) |
| Target Locations / Products | Yamagata Main Line Voltage Increase Extension Tower Construction (Part 2), Construction Section 2, Sakata, Yamagata Prefecture, and other locations. Seventeen of the 112 new towers, covering approximately 10.1 km of 500 kV transmission lines |
| Impact on Earnings Forecast | The portion completed in September 2026 has already been reflected in the earnings forecast announced on 7 August 2026. The company will promptly disclose any revisions if it becomes necessary to revise the forecast figures. |
| Outlook | The construction period is from September 2026 to March 2033. Operations are scheduled to commence in October 2033. The company will promptly disclose any revisions if it becomes necessary to revise the forecast figures. |
| Planned follow-up disclosure | The company will promptly disclose any revisions if it becomes necessary to revise the forecast figures. The timing for finalising the contract value is Not disclosed. |
Items this document does not state (18)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The company does not state the specific reason for receiving the order, but explains that the construction is part of a wide-area power grid development plan led by the Organization for Cross-regional Coordination of Transmission Operators (OCCTO).