Komori
Occurring Fact253AETS Group Co.,Ltd.Construction and Materials

Notice Regarding the Completion of Construction Work at a Consolidated Subsidiary

ETS Line Co., Ltd., a consolidated subsidiary, completed by May 2026 the removal and installation of extra-high-voltage substation equipment in Toyota, Aichi Prefecture.

Worth reading
25Immaterial
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Neutral
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Conditional
How definitive the wording is.

Completion of construction work by a subsidiary

Subject Entity

ETS Line Co., Ltd. (a consolidated subsidiary of the filing company)

Target Locations / Products

Toyota, Aichi Prefecture. Removal and installation of extra-high-voltage substation equipment. The customer was a foreign-affiliated solar power plant operator.

OccurrenceMay 2026 (specific completion date: Not disclosed)
This disclosure06/23/2026
Impact on Earnings Forecast

The portion of the work completed between October 2025 and May 2026 has already been reflected in the "Notice Regarding Revisions to Earnings Forecasts" announced on 14 May 2026. If it becomes necessary to revise the forecast figures going forward, the company will promptly disclose the revisions.

Outlook

If it becomes necessary to revise the forecast figures going forward, the company will promptly disclose the revisions.

Planned follow-up disclosure

If it becomes necessary to revise the forecast figures, the company will promptly disclose the revisions.

Event that occurred
ItemDetails
Event nameCompletion of construction work by a subsidiary
Date of occurrenceMay 2026 (specific completion date: Not disclosed)
Subject EntityETS Line Co., Ltd. (a consolidated subsidiary of the filing company)
Target Locations / ProductsToyota, Aichi Prefecture. Removal and installation of extra-high-voltage substation equipment. The customer was a foreign-affiliated solar power plant operator.
Impact on Earnings ForecastThe portion of the work completed between October 2025 and May 2026 has already been reflected in the "Notice Regarding Revisions to Earnings Forecasts" announced on 14 May 2026. If it becomes necessary to revise the forecast figures going forward, the company will promptly disclose the revisions.
OutlookIf it becomes necessary to revise the forecast figures going forward, the company will promptly disclose the revisions.
Planned follow-up disclosureIf it becomes necessary to revise the forecast figures, the company will promptly disclose the revisions.
Items this document does not state (18)
Date recognized / date notice receivedCauseAmount of Impact on Business PerformanceAccounting period in which recognizedType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionSuspended operationsScheduled resumption dateInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Completion of Construction Work at a Consolidated Subsidiary | ETS Group Co.,Ltd. (253A) timely disclosure | Komori