Shinwa Wise Holdings (2437) · RiskMaterialised
Project Revisions Due to Competition and Delays in Grid Interconnection
First written in FY2016. 2 of 4 entries say "Materialised", first in FY2018-Q2. Latest entry: FY2018.
4entries
3years
0from disclosures
How it moved
Same theme, other companies
Revisions to Sales Plans Due to Competition for Solar Power Projects and Grid Interconnection DelaysA theme 7 companies write about · 8 as a headwind · 0 as a tailwind
Shinwa Wise Holdings moved to the "Worse" side of this theme in 2018.
1 other company's latest entry also says "Materialised".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2018MaterialisedAnnual report
「50kW級の低圧型太陽光発電施設の販売事業に関しましては、改正FIT法施行による一時的な市場の混乱で、売電の開始目処が把握できる発電施設の仕入れが困難な状況が続き、仕入れ後の連系前工事の遅延などが重なったため、引き続き利回り商品としての需要はあったものの計画どおりの供給が当期中に間に合わず、18基が次年度に回ることとなり、当連結会計年度は40基の販売実績となりました。」
連系可能案件の仕入れ困難と連系前工事の遅延により、販売計画の一部が次年度へ繰り越される事象が通期でも発生した。 - FY2018-Q3RestatedAnnual report
「50kW級の低圧型太陽光発電施設の販売事業に関しましては、電力会社の系統連系が確実に可能な案件の厳選と仕入れに時間を要し、当第3四半期連結累計期間は17基の販売実績に止まりました。」
系統連系が確実に可能な案件の厳選・仕入れに時間を要し、販売実績が17基にとどまる影響を引き続き記載している。 - FY2018-Q2MaterialisedAnnual report
「確実に連系が可能な仕入案件の厳選に当初予想よりもはるかに多くの時間を費やすこととなり、当第2四半期連結累計期間は50基の販売計画に対し13基の販売実績に止まりました。」
連系可能な案件の厳選に時間を要し、販売計画50基に対して実績13基となる計画遅延・未達が実際に発生した。 - FY2016First statedAnnual report
「電力会社による系統連系手続の遅れや系統連系そのものの見合わせ等が発生した場合には、当社グループの事業が当初の計画通り進まず、事業計画そのものの見直しを迫られる可能性もあり」
太陽光発電施設販売における競合、系統連系手続、許認可や計画遅延をリスクとしている。