- FY2026AdvancedAnnual report
「During the consolidated fiscal year, the company made total capital expenditures of ¥39,855 million on property, plant and equipment and intangible fixed assets.」
The company made ¥39,855 million in capital expenditures during the fiscal year and set capital expenditures for the following year at ¥20,050 million, continuing to strengthen its infrastructure, including security equipment and networks. - FY2025-H1Increase in costs related to the 3G network shutdownAnnual report
「Operating profit amounted to ¥15,603 million, down 12.5% year on year, due to the implementation of base-pay increases, higher costs related to the 3G network shutdown, and an increase in the allowance for doubtful accounts, among other factors.」
Higher costs related to the 3G network shutdown became apparent as a factor weighing on operating profit, along with base-pay increases and other factors. - FY2023-Q2Increase in system-related costs becoming apparentAnnual report
「The company was unable to offset the decline in sales related to the Tokyo 2020 Games in the previous year and the increase in system-related costs, among other factors.」
The increase in system-related costs was cited, together with the decline in sales related to the Tokyo 2020 Games, as a factor weighing on consolidated results. - FY2022AdvancedAnnual report
「Selling, general and administrative expenses amounted to ¥82,715 million, reflecting the recognition of ¥2,392 million in outsourcing fees and ¥903 million in depreciation expenses following the launch of the sales administration system.」
The renewal of the core and operating systems progressed to the specific implementation stage, with the launch of the sales administration system. - FY2021-Q1RestatedAnnual report
「There were no significant changes to the capital expenditure plan, including planned capital expenditures, as of the end of the previous consolidated accounting period during the first quarter of the current consolidated cumulative period.」
The company stated that there had been no significant changes since the end of the previous consolidated fiscal year to the capital expenditure plan, including investment in core systems. - FY2020AdvancedAnnual report
「To support the expansion of its security-focused business and improve its capabilities, the Group made total capital expenditures of ¥14,066 million on property, plant and equipment and intangible fixed assets during the consolidated fiscal year.」
The company continued capital investment, including in core systems. Capital expenditures totaled ¥14,066 million in the fiscal year, with a plan of ¥16,800 million for the following year. - FY2019AdvancedAnnual report
「Of these expenditures, capital expenditures for other intangible fixed assets primarily consisted of software under construction related to investment in core systems scheduled for completion in the following fiscal year and beyond.」
Software under construction related to the core-system investment amounted to ¥3,790 million, while the capital expenditure plan for network systems and other items over the following year was set at ¥6,400 million. - FY2019-Q1Impact of the system renewal becoming apparentAnnual report
「As a result, revenue from the security business was ¥84,174 million, up 1.4% year on year. In terms of profit, operating income was ¥7,151 million, down 3.6% year on year, partly due to higher personnel expenses and the replacement of the core system.」
The company stated that the renewal of its core systems was under way and that its impact had been reflected in operating profit in the security business. - FY2018First statedAnnual report
「Capital expenditures for other intangible fixed assets primarily consisted of software under construction related to investment in core systems scheduled for completion in the following fiscal year and beyond.」