Agreement Signed for a Project to Install Solar Power Generation Facilities at Sapporo City Teine Water Reclamation Plant Using a PPA Model

NJS signed an agreement with Sapporo City for an on-site PPA project to install solar power generation facilities at the Teine Water Reclamation Center and use the electricity generated on-site. The project will install approximately 689 kW of capacity, with first-year generation expected to reach approximately 860,000 kWh and annual greenhouse gas emissions reductions expected to total approximately 378 t-CO₂.

Worth reading
62In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
689
kW
Wording
Conditional
How definitive the wording is.

Announced details

On-site PPA (electricity supply using solar power generation facilities and associated equipment)
Applicable field (uses covered by this announcement)

Sewage treatment facilities, water and sewerage, on-site self-consumption, and decarbonization

Launch datenot disclosed (in principle, electricity will be supplied for 20 years from the start of supply)
Contract Date10 August 2026
What the company reported numerically
Quantitative Effects

Expected first-year annual generation of approximately 860,000 kWh and expected annual reduction of approximately 378 t-CO₂ in greenhouse gas emissions

Usage history

NJS has participated as a group member in 3 PPA projects to date.

Relationship between the counterparty and the company
NJS Co.,Ltd.2325
Relationship with the Company

NJS is a member company of the NJS and NTT-ME Sapporo City Teine Water Reclamation Center PPA Project Group, represented by NTT-ME Corporation. NJS signed an agreement with Sapporo City concerning this project.

CounterpartySapporo City

Sapporo City, a local government that owns the Teine Water Reclamation Center. Other information, including its address, representative, capital and year of establishment, is not disclosed.

Location (as indicated in this announcement)

265-8 Teine Yamaguchi, Teine-ku, Sapporo, Hokkaido (Teine Water Reclamation Center)

Approximately 689 kW of installed solar power generation capacity

In this announcement the company addresses none of Contract Value / Offering price / Impact on Business Performance.

Source (materials cited by the company)

Guidebook for Calculating the Effects of Global Warming Countermeasures (revised March 2025). CO2 emissions factor: 0.438 kg-CO2/kWh

Announced details
ItemDetails
Names of Products / Services CoveredOn-site PPA (electricity supply using solar power generation facilities and associated equipment)
CounterpartySapporo City
Counterparty overviewSapporo City, a local government that owns the Teine Water Reclamation Center. Other information, including its address, representative, capital and year of establishment, is not disclosed.
Relationship with the CompanyNJS is a member company of the NJS and NTT-ME Sapporo City Teine Water Reclamation Center PPA Project Group, represented by NTT-ME Corporation. NJS signed an agreement with Sapporo City concerning this project.
Contract Date10 August 2026
Launch datenot disclosed (in principle, electricity will be supplied for 20 years from the start of supply)
Applicable areaSewage treatment facilities, water and sewerage, on-site self-consumption, and decarbonization
Location265-8 Teine Yamaguchi, Teine-ku, Sapporo, Hokkaido (Teine Water Reclamation Center)
Location scaleApproximately 689 kW of installed solar power generation capacity
Quantitative EffectsExpected first-year annual generation of approximately 860,000 kWh and expected annual reduction of approximately 378 t-CO₂ in greenhouse gas emissions
Usage historyNJS has participated as a group member in 3 PPA projects to date.
SourceGuidebook for Calculating the Effects of Global Warming Countermeasures (revised March 2025). CO2 emissions factor: 0.438 kg-CO2/kWh
Items this document does not state (6)
Contract ValueOffering priceAward/certification nameAwarding / certifying bodyRegistration number and expiry dateImpact on Business Performance

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

To decarbonize the Teine Water Reclamation Center, reduce greenhouse gas emissions, and expand the use of renewable energy.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Agreement Signed for a Project to Install Solar Power Generation Facilities at Sapporo City Teine Water Reclamation Plant Using a PPA Model | NJS Co.,Ltd. (2325) timely disclosure | Komori