Announced details
Water supply facilities; design, construction, operation and maintenance of a new water purification plant
NJS is responsible for designing water supply facilities as a member company of the 協和機電工業 Group. 冨洋設計株式会社 is a group company of the Company. NJS has entered into a project agreement with Nagasaki City and Nagayo Town for this project.
Nagasaki City and Nagayo Town. The disclosure states that, as the entities responsible for managing the water purification plants, Nagasaki City manages the Urakami and Michinoo water purification plants, while Nagayo Town manages the No. 1 water purification plant. Other details are not disclosed.
Maximum planned daily water supply capacity of 29,535 m3/day
¥26,281,850,000 (excluding consumption tax); ¥28,910,035,000 (including consumption tax)
The company does not address Offering price / Impact on Business Performance.
| Item | Details |
|---|---|
| Names of Products / Services Covered | Nagasaki City and Nagayo Town New Water Purification Plant Joint Development Project |
| Counterparty | Nagasaki City, Nagayo Town |
| Counterparty overview | Nagasaki City and Nagayo Town. The disclosure states that, as the entities responsible for managing the water purification plants, Nagasaki City manages the Urakami and Michinoo water purification plants, while Nagayo Town manages the No. 1 water purification plant. Other details are not disclosed. |
| Relationship with the Company | NJS is responsible for designing water supply facilities as a member company of the 協和機電工業 Group. 冨洋設計株式会社 is a group company of the Company. NJS has entered into a project agreement with Nagasaki City and Nagayo Town for this project. |
| Contract Value | ¥26,281,850,000 (excluding consumption tax); ¥28,910,035,000 (including consumption tax) |
| Contract Date | 25 June 2026 (the same date as the announcement date stated in the disclosure) |
| Launch date | The design and construction period began on 10 February 2026 (the actual and contractually specified period). The operation and maintenance period is scheduled to begin on 1 April 2033. |
| Applicable area | Water supply facilities; design, construction, operation and maintenance of a new water purification plant |
| Location scale | Maximum planned daily water supply capacity of 29,535 m3/day |
Items this document does not state (9)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.To consolidate and close multiple aging water purification plants in light of future water demand, thereby ensuring a stable water supply and improving the efficiency of facility operations.