Construction of a New Headquarters Building Through Redevelopment of the Existing Headquarters
First written in FY2025. 2 of 3 entries say "Softened", first in 2026-06-06. Latest entry: FY2026.
Kanda Tsushinki moved to the "Worse" side of this theme in 2026.
The whole theme swung hardest in 2026: 1 of 6 companies on the "Worse" side.
0 other companies' latest entry also says "Softened".
- FY2026SoftenedAnnual report
「Filing company New head office building (Chiyoda-ku, Tokyo) Buildings and structures (Replacement of head office building) 1,314,500 27,048 Internal funds March 2025 December 2027」
The company has disclosed total planned investment of ¥1,314.5 million for the new head office building, ¥27.048 million already paid, and funding through internal funds. The scheduled completion date changed from August 2027 in the previous fiscal year to December 2027. - 2026-06-06SoftenedGeneral Meetings of Shareholders
「The new head office is scheduled for completion in the fiscal year ending March 2028.」
The completion timing has been pushed back, with the previous target of August 2027 updated to completion in the fiscal year ending March 2028. - FY2025First statedAnnual report
「Filing company New head office building (Chiyoda-ku, Tokyo) Buildings and structures (Replacement of head office building) 1,314,500 8,600 Internal funds March 2025 August 2027 (Note) The existing building will be demolished before reconstruction.」
The company has, for the first time, disclosed a plan to demolish the existing head office building and replace it with a new head office building. The total planned investment is ¥1,314.5 million, the amount already paid is ¥8.6 million, and completion is scheduled for August 2027.