Construction of a New Mishima Plant and Transition to a Dual-Site Production System

First written in FY2024. 2 of 7 entries say "Advanced", first in FY2025-H1. Latest entry: FY2026.

7entries
3years
2from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2024AdvancedFY2025-H1SoftenedFY20252024: 120242025: 220252026: 42026
Same theme, other companies
Strengthening BCP through the dispersion of headquarters, logistics and production sitesA theme 29 companies write about · 0 as a headwind · 29 as a tailwind

9 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 29 companies compared. The sentences above are computed from all 29.
Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「We will improve productivity and quality by strengthening the antigen testing production system centered on the Mt. Fuji Mishima Plant, automating manufacturing and testing lines, and optimizing production planning using data, AI and other technologies.」

    Following the start of operations at the new plant, the company has been advancing automation and data- and AI-based production planning optimization on the assumption of production at two sites.
  2. FY2026-H1AchievedAnnual report

    「The Fujisan Mishima Plant will commence full-scale operations as scheduled from 2 February 2026.」

    The new plant, which had been scheduled to begin operations in February 2026, reached the stage of commencing full-scale operations as scheduled on 2 February.
  3. FY2025SoftenedAnnual report

    「As a fundamental measure, we are constructing a new plant in Mishima City and aim to begin operations in February 2026.」

    The target start date was pushed back from December 2025 to February 2026. Investment in the buildings and production equipment of the New Mishima Plant continued, with plans to increase monthly production capacity from 1.3 million tests to 3.9 million tests and disclosure of plant-related assets exceeding ¥9.7 billion.
  4. FY2025-H1AdvancedAnnual report

    「This was mainly due to an increase in trade receivables accompanying the substantial growth in revenue resulting from the influenza outbreak in December, as well as an increase in construction in progress related to the construction of the new plant. Cash decreased by ¥4,664.086 million through investing activities, mainly due to payments for the acquisition of property, plant and equipment associated with construction of the new plant.」

    Construction in progress related to the new plant increased to ¥7,610.332 million, and ¥4,118.389 million was spent on property, plant and equipment, indicating that the construction plan had progressed to the stage of concrete investment and asset recognition. The disclosure did not state that operations had begun or that the two-site production system had been completed.
  5. FY2024First statedAnnual report

    「As a fundamental measure, we are constructing a new plant in Mishima City and aim to begin operations in December 2025.」

    The new plant is intended to expand existing lines, accommodate new products, introduce factory automation, provide inventory storage, and establish a two-site production system for BCP. Monthly production capacity is expected to increase from 1.3 million tests to 3.9 million tests.
Moved together

"Risk of operational interruption under a single-site structure centered on the Kamishima Plant" moved the same way as this thread, in the same document, in 4 of its 7 moves.

432★123
  1. ★This thread
  2. 1Risk of operational interruption under a single-site structure centered on the Kamishima Plant4×
  3. 2Stable, Sustained Dividends Based on a Payout Ratio of Approximately 30%3×
  4. 3Dependence on Sales of COVID-19-Related Products2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for TAUNS Laboratories yet. It last moved in the Earnings of 2026-08-13: "Achieved".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Construction of a New Mishima Plant and Transition to a Dual-Site Production System | TAUNS Laboratories,Inc. (197A) | Komori