Schedule overruns for large-scale construction projects
First written in FY2026-H1. . Latest entry: FY2026.
The whole theme swung hardest in 2026: 11 of 25 companies on the "Worse" side.
1 other company's latest entry also says "Other".
- FY2026Deferral of large-scale construction projects to the following fiscal year or later affects full-year resultsAnnual report
「In terms of sales, the decrease in work volume during the off-season for periodic repair work at domestic chemical plants and oil and natural gas plants, together with the deferral of scheduled completion dates for some construction projects to the following fiscal year or later due to changes in the external environment and other factors, resulted in consolidated net sales of ¥53,693 million, down ¥4,373 million, or 7.5%, from the previous consolidated fiscal year.」
The schedule overruns for some large-scale construction projects disclosed in the interim period became a factor behind the decline in full-year net sales as the projects were deferred to the following fiscal year or later. - FY2026-H1First statedAnnual report
「Among these projects, we primarily addressed large-scale construction projects at domestic plants, but changes in the external environment and other factors caused the scheduled completion dates for some construction projects to be pushed back to the third quarter or later.」
The disclosure newly states that changes in the external environment and other factors pushed back the scheduled completion dates for some large-scale domestic construction projects to the third quarter or later.