Project Delays Due to Longer Lead Times for Materials and Equipment
First written in FY2025-H1. 1 of 2 entries say "Dropped", first in FY2025. Latest entry: FY2025.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Project Progress Risks from Shortages of Materials and Equipment and Delivery DelaysA theme 41 companies write about · 43 as a headwind · 0 as a tailwind
The whole theme swung hardest in 2026: 9 of 23 companies on the "Worse" side.
2 other companies' latest entry also says "Dropped".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 41 companies compared. The sentences above are computed from all 41.Full recordFilings, disclosures and news, newest first
- FY2025DroppedAnnual report前中間期に記載されていた資材・機器類の納期長期化による工期影響は、本有価証券報告書の事業等のリスクおよび経営環境の記載で明示的に確認できない。
- FY2025-H1First statedAnnual report
「建設業界におきましては、公共投資及び民間投資ともに前年度と同水準で底堅く推移しておりますが、建設コストの高止まりに加え、資材や機器類の納期が長期化している事で工期に影響を及ぼす等、楽観できない状況も見受けられます。」
資材・機器類の納期長期化と、それによる工期への影響を、当中間連結会計期間の建設業界の状況として初めて独立したテーマとして抽出した。個別工事の遅延件数や金額は記載されていない。