Jgc Holdings (1963) · RiskCited as achieved
Delivery delays and higher construction costs caused by adverse weather at a US petrochemical project
First written in FY2017-Q2. 1 of 4 entries say "Restated". Latest entry: FY2020.
4entries
5years
0from disclosures
How it moved
Same theme, other companies
Risk of construction delays and additional costs due to natural disastersA theme 20 companies write about · 21 as a headwind · 0 as a tailwind
The whole theme swung hardest in 2025: 3 of 6 companies on the "Worse" side.
0 other companies' latest entry also says "Cited as achieved".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 20 companies compared. The sentences above are computed from all 20.Full recordFilings, disclosures and news, newest first
- FY2020Cited as achievedAnnual report
「加えて米国および中東のプロジェクトにおいて、想定以上の天候不順、ビザ発給の遅れによる労働力確保の難しさなどが原因となり、建設工事費用が増加したこと等により、2016年度に多額の損失を計上するに至ったことも業績に影響いたしました。」
米国・中東プロジェクトの天候不順等による建設費増加を、過去の業績悪化要因として引用している。 - FY2018-Q3DroppedAnnual report本ファイリングでは、米国石油化学プロジェクトの天候不順による納期遅延・建設費増加についての個別の記載はない。
- FY2017-Q3RestatedAnnual report
「米国で遂行中の石油化学プロジェクトにおいて、想定以上の天候不順に起因する建設工事費用の大幅な増加が見込まれる状況となりました。」
米国石油化学プロジェクトについて、想定以上の天候不順を原因とする建設工事費用増加のリスクが継続している。 - FY2017-Q2First statedAnnual report
「米国で遂行中の石油化学プロジェクトにおいて、想定以上の天候不順に起因する納期遅延による大幅な建設工事費用の増加および円高の進行により、当社グループの当第2四半期連結累計期間の業績等については、以下のとおりとなりました。」
想定以上の天候不順による納期遅延が発生し、建設工事費用の大幅な増加が見込まれる状況を記載している。